Eskom load-shedding for Monday

Eskom has announced Stage 2 load-shedding on Monday from 17:00 to 22:00.

This is because the power system is severely constrained, the power utility said.
 

BTTB

Executive Member
Joined
Feb 6, 2004
Messages
8,195
"Earlier today, the power utility had 3,049 MW offline on planned maintenance and 14,985 MW of capacity unavailable due to breakdowns"


I'm pretty sure that all these Eskom notices over the last couple of years almost always includes a plus minus 15,000MW outage, due to variable reasons.
Beginning to think that the 15K is just a way to get us thinking that at some stage we'll gain that capacity back and load shedding will stop?

I believe we are being bullshirtted here, the bulk of that 15,000MW is never going to come online again.
 

Lupus

Honorary Master
Joined
Apr 25, 2006
Messages
50,973
I don't really understand the logic behind that. Do the reasons for load reduction (overloading of substations) suddenly disappear during loadshedding?
No that's why when it happens those areas log faults
 

Jan

Who's the Boss?
Staff member
Joined
May 24, 2010
Messages
10,412
Update from Eskom:

  • A generation unit each at Kriel, Grootvlei and Majuba power stations tripped this afternoon.
  • A unit each at Hendrina and Kendal power stations returned to service
  • The return to service of a generation unit each at Kusile, Matimba and Lethabo power stations, as well as two units each at Hendrina and three at Tutuka power stations have been delayed
  • 3 049MW on planned maintenance, while another 15 943MW of capacity is unavailable due to breakdowns.
 
  • Like
Reactions: Yuu

Lupus

Honorary Master
Joined
Apr 25, 2006
Messages
50,973
Update from Eskom:

  • A generation unit each at Kriel, Grootvlei and Majuba power stations tripped this afternoon.
  • A unit each at Hendrina and Kendal power stations returned to service
  • The return to service of a generation unit each at Kusile, Matimba and Lethabo power stations, as well as two units each at Hendrina and three at Tutuka power stations have been delayed
  • 3 049MW on planned maintenance, while another 15 943MW of capacity is unavailable due to breakdowns.
Yup it actually went down from the earlier announcement. I mean this year we haven't even hit a 60% EAF.
 