Just received the following:
For your convenience have a look at the rollout schedule below to get a better understanding of which area of the build you fall into. The rollout schedule indicates that:
Construction will happen in the specified area
Each area will "go live" once civil and fibre work is completed in that area
The Map will show you a "construction start date" for when trenching activity can be expected in your area
It will also show you a "forecast fibre ready date" for when you can expect us to start installing into homes in your areas
Currently, the status of the areas is as follows:
Area 1: Kick-off meeting scheduled for 29 Jan
Area 2: Kick-off meeting scheduled for 29 Jan
Area 3: Kick-off meeting scheduled for 29 Jan
Area 4: Kick-off meeting scheduled for 29 Jan
Area 5: Awaiting confirmation of the kick-off date
Area 6: Kick-off meeting scheduled for 29 Jan
Area 7: Awaiting confirmation of the kick-off date
Area 8: Awaiting confirmation of the kick-off date
The re-instatement of your driveway and other trenched areas can take up to 3 weeks to complete, your patience during this time is appreciated.
Please keep in mind that this is a large-scale civils project and the forecast dates can change. As grateful as we are for the rain, this can also affect the build. We will keep you updated on any date changes.
Map access seems restricted atm but the link is:
https://www.google.com/maps/d/u/0/v...53&z=14&mid=17qYiAdz4YpoixVDzLq4WD4o8YKV3shET