Brakfontein Substation Update

8 April 2025 |

10h00

Pressure testing of the busbars are in progress, — this is essential before any power can be safely restored. ONGOING

Technical efforts underway:
T4 Ring Main Units (RMUs) the bypass of damaged panels. COMPLETED and CABLES IDENTIFIED
Excavations for new cable installations. COMPLETED
Burnt cables removal - COMPLETED
MultiCore cables installations - ONGOING
- Transformer A- completed
- Transformer B - in progress
- Transformer C - in progress
AN ETR WILL BE SUPPLIED TONIGHT, AS SOME IMPORTANT ACTIONS STILL NEEDS TO TAKE PLACE TODAY.
WORK IS AT 70% COMPLETE
Thank you for your continued patience and understanding — we are all in this together.
#BrakfonteinUpdate #CenturionPower #SubstationRepair #StayInformed