Binary_Bark
Forging
- Joined
- Feb 24, 2016
- Messages
- 38,582
Recent information has emerged that puts the blame for the incomplete Hazelmere Dam project squarely on the doorstep of the Department of Water and Sanitation (DWS).
Following the previous article in the Courier (Hazelmere Botch-Up, November 15), a project engineer who worked on the Hazelmere site, who asked not to be named, said the mega-project to double the dam’s water capacity came to a halt after the department failed to come up with about R40 million needed by Group Five, the contractors on the project, to buy specialised material to complete the work.
However, escalation costs have now snowballed the estimated cost to finish the remaining four percent of the project to over R100 million. The project has cost R526 million so far.
Responding to questions from the Courier, Group Five spokesperson Heidi Geldenhuys confirmed that Group Five terminated the contract on October 9, 2018 following months of failing to get payment from the department and moved off site in February this year.
northcoastcourier.co.za
Following the previous article in the Courier (Hazelmere Botch-Up, November 15), a project engineer who worked on the Hazelmere site, who asked not to be named, said the mega-project to double the dam’s water capacity came to a halt after the department failed to come up with about R40 million needed by Group Five, the contractors on the project, to buy specialised material to complete the work.
However, escalation costs have now snowballed the estimated cost to finish the remaining four percent of the project to over R100 million. The project has cost R526 million so far.
Responding to questions from the Courier, Group Five spokesperson Heidi Geldenhuys confirmed that Group Five terminated the contract on October 9, 2018 following months of failing to get payment from the department and moved off site in February this year.
Millions wasted as Hazelmere Dam project stalled after Department's failure to pay | North Coast Courier
However, escalation costs have now snowballed the estimated cost to finish the remaining four percent of the project to over R100 million. The project has cost R526 million so far.