Rolling Blackouts updates: Sunday 26 July 2015 [Stage 2: 8am - 10pm]

Gtx Gaming

Gtx Gaming
Joined
Aug 25, 2008
Messages
25,509
Few area's in cape town are being skipped ,steenbras to the rescue!

COCT is only on stage 1.
 

Beachless

Executive Member
Joined
Oct 6, 2010
Messages
6,003
I must say I really dont believe that the load on a sunday morning is enough to require loadshedding this coupled by the fact that they refuse to release the stats really worries me.
 

Creag

The Boar's Rock
Joined
May 19, 2009
Messages
43,527
Randpark Ridge is out now. Do not know if it's load shedding or a fault. Darn critters!
 

cavedog

Honorary Master
Joined
Oct 19, 2007
Messages
22,661
I must say I really dont believe that the load on a sunday morning is enough to require loadshedding this coupled by the fact that they refuse to release the stats really worries me.

They must be refilling the dam.... Depending on how low it was could take the whole weekend to fill back up.

Being on stage 2 I suspect that there might be some other units down too causing the extra shortfall. I totally agree. Eskom needs to tell the public what is going on....
 

MickeyD

RIP
Joined
Oct 4, 2010
Messages
139,117
Still nothing in PE as the metro staff are on strike. Feel bad for some areas out since Friday.

Good luck, bwana!
 

MickZA

Executive Member
Joined
Jan 19, 2007
Messages
7,575
Still nothing in PE as the metro staff are on strike. Feel bad for some areas out since Friday.

Good luck, bwana!
Can't help but feel sorry for Danny as well, guess we'll have to wait until Tuesday before the details of the "scarce skills" allowance dispute emerge.
 

Dan C

Honorary Master
Joined
Nov 21, 2005
Messages
36,659
Won't be surprised if we see stage 3 soon this winter...
 

garyc

Expert Member
Joined
Jun 30, 2010
Messages
3,632
So:

- Koeberg is down for refueling for a while.
- Duvha unit 3 has been down since the explosion last year. Opinion is still divided if it can ever be returned to service, but this will take years to repair if it is feasible.
- Majuba is limping after the silo collapse. This will also be a long-term project to fix.
- The boiler damage at Lethabo will take a little while still to fix.
- 64% of the total installed capacity is beyond mid-life. These stations are now into their less reliable and higher maintenance phase. The number of MW not available due to breakdowns was approximately 1800 in FY2009. It has now grown steadily year-on-year and now sits at 5500.

Keep those laptop batteries charged unless you believe that the new power stations will be coming online faster than we loose current capacity.
 

bwana

MyBroadband
Super Moderator
Joined
Feb 23, 2005
Messages
89,382
So:

- Koeberg is down for refueling for a while.
- Duvha unit 3 has been down since the explosion last year. Opinion is still divided if it can ever be returned to service, but this will take years to repair if it is feasible.
- Majuba is limping after the silo collapse. This will also be a long-term project to fix.
- The boiler damage at Lethabo will take a little while still to fix.
- 64% of the total installed capacity is beyond mid-life. These stations are now into their less reliable and higher maintenance phase. The number of MW not available due to breakdowns was approximately 1800 in FY2009. It has now grown steadily year-on-year and now sits at 5500.

Keep those laptop batteries charged unless you believe that the new power stations will be coming online faster than we loose current capacity.
Isnt that from the end of August?
 

Mephisto_Helix

Resident Postwhore
Joined
Jan 29, 2008
Messages
29,723
having MyBB open to look for the loadshedding - pass over it because the thread title is silly now
 

A Non Blonde

Senior Member
Joined
Nov 1, 2009
Messages
588
I must say I really dont believe that the load on a sunday morning is enough to require loadshedding this coupled by the fact that they refuse to release the stats really worries me.

Perhaps attributed to "building up reserves" for the week ahead and generally less inconvenient over a weekend.
 

biometrics

Honorary Master
Joined
Aug 7, 2003
Messages
71,858
I must say I really dont believe that the load on a sunday morning is enough to require loadshedding this coupled by the fact that they refuse to release the stats really worries me.

Imo they are saving on diesel by not running the ocgt weekends. Punishment for not getting another increase.
 
Top