Eskom Hld SOC Ltd ‏@Eskom_SA 1 hour ago
#PowerAlert #load_shedding stage 2 will be implemented from 08h00 to 22h00 today. Please use energy efficiency ways to keep warm today.

Edit: Confirmed by City of Cape Town:
@CityofCTAlerts
Stage 2- Area 7 and 15 Start time 08:00 End time 10:30.

Edit #2: http://www.capetown.gov.za/en/electricity/Pages/LoadShedding.aspx
THE CITY WILL CHANGE FROM STAGE 2 TO STAGE 1 LOADSHEDDING FROM 12:00 TO 22:00 DUE TO SPARE GENERATION
 
Last edited:

bwana

B MyBroadband
Super Moderator
Joined
Feb 23, 2005
Messages
72,132
My power still hasn't been restored from last night's R[SUP]3[/SUP]. :eek:
 
Last edited:

MickZA

Executive Member
Joined
Jan 19, 2007
Messages
7,576
My power still hasn't been restored from last night's R[SUP]3[/SUP]. :eek:
We weren't cut off last night as scheduled so 11:00 today's the litmus test for our area.

Meanwhile, in other news:

Weather.jpg

... it's still raining - thx to thehuman for the stats.
 

MickZA

Executive Member
Joined
Jan 19, 2007
Messages
7,576
Areas still out includes parts of: Seaview, Beachview, Kini Bay, Summerstrand and Mount Croix.
Does that mean PE is meeting its overall load-shedding requirements and the rest of us are off the hook :whistling:
 

Arthur

Honorary Master
Joined
Aug 7, 2003
Messages
23,917
It's interesting to see the voltage changes just before LS kicks in. Spec supply here is 240V, but about two minutes before LS that drops to 236-237V, and then rises to 239-240V and then cut.
 

supersunbird

Honorary Master
Joined
Oct 1, 2005
Messages
47,966
It's interesting to see the voltage changes just before LS kicks in. Spec supply here is 240V, but about two minutes before LS that drops to 236-237V, and then rises to 239-240V and then cut.
According to my UPS software, I am currently receiving 225V
 

cavedog

Honorary Master
Joined
Oct 19, 2007
Messages
13,671
Eskom not going to be happy
Eskom usually have a decent buffer I think.

For us the Municipality got their schedules totally wrong.... They have times like block 1 8am to 10:30am and then block 2 11am to 13:30 so between the times there is 30min the that whole area got power. Usually they should overlap to but I guess Eskom don't care about that 30min or it is simply not significant enough.

I won't be surprised if Eskom got like 500MW buffer or so.
 