Eskom Hld SOC Ltd ‏@Eskom_SA 1 hour ago
#PowerAlert #load_shedding stage 2 will be implemented from 08h00 to 22h00 today. Please use energy efficiency ways to keep warm today.

Edit: Confirmed by City of Cape Town:
@CityofCTAlerts
Stage 2- Area 7 and 15 Start time 08:00 End time 10:30.

Edit #2: http://www.capetown.gov.za/en/electricity/Pages/LoadShedding.aspx
THE CITY WILL CHANGE FROM STAGE 2 TO STAGE 1 LOADSHEDDING FROM 12:00 TO 22:00 DUE TO SPARE GENERATION
 
Last edited:

bwana

B MyBroadband
Super Moderator
Joined
Feb 23, 2005
Messages
70,999
#3
My power still hasn't been restored from last night's R[SUP]3[/SUP]. :eek:
 
Last edited:

MickZA

Executive Member
Joined
Jan 19, 2007
Messages
7,577
#8
My power still hasn't been restored from last night's R[SUP]3[/SUP]. :eek:
We weren't cut off last night as scheduled so 11:00 today's the litmus test for our area.

Meanwhile, in other news:

Weather.jpg

... it's still raining - thx to thehuman for the stats.
 

Arthur

Honorary Master
Joined
Aug 7, 2003
Messages
23,253
#10
It's interesting to see the voltage changes just before LS kicks in. Spec supply here is 240V, but about two minutes before LS that drops to 236-237V, and then rises to 239-240V and then cut.
 

supersunbird

Honorary Master
Joined
Oct 1, 2005
Messages
45,704
#11
It's interesting to see the voltage changes just before LS kicks in. Spec supply here is 240V, but about two minutes before LS that drops to 236-237V, and then rises to 239-240V and then cut.
According to my UPS software, I am currently receiving 225V
 

cavedog

Honorary Master
Joined
Oct 19, 2007
Messages
11,661
#19
Eskom not going to be happy
Eskom usually have a decent buffer I think.

For us the Municipality got their schedules totally wrong.... They have times like block 1 8am to 10:30am and then block 2 11am to 13:30 so between the times there is 30min the that whole area got power. Usually they should overlap to but I guess Eskom don't care about that 30min or it is simply not significant enough.

I won't be surprised if Eskom got like 500MW buffer or so.
 