Warning over ‘stage 10’ load shedding – and what it means for South Africa

blaaislaai

Executive Member
Joined
Mar 6, 2007
Messages
5,740
New energy expert?

Let's just get to stage 7 first before triggering the public with a stage we might not even get.
 

Sinbad

Honorary Master
Joined
Jun 5, 2006
Messages
81,151
Each stage number corresponds to 1000MW shed from the grid. It's not arbitrary. The upper stage limit is the country's maximum electricity demand, in MWs, divided by 1000.

Or am I missing something here?
The 1000 is arbitrarily selected
 

AstroTurf

Lucky Shot
Joined
May 13, 2010
Messages
30,534
I have a laptop here that one of the managers dropped a glass of water on.

I told said manager that I will give the laptop an ISO bath and there is a 50/50 it will work again after.

This is very much like that.

An Educated Thumsuck.
 

konfab

Honorary Master
Joined
Jun 23, 2008
Messages
36,120
South Africa's load shedding stages are completely arbitrary, and there is, theoretically, no upper limit to how high they could go.

There is a theoretical hard limit of how high it can be, it is the installation capacity of the country in GW + whatever neighbouring countries are able to export. Which is about 58 (Yes I know there are probably a few stages lost with losses). You cannot have more power reduction than you have installed capacity.
 

porchrat

Honorary Master
Joined
Sep 11, 2008
Messages
34,278
Yes I seem to recall it being 2000 way back when
hmmm... seem to vaguely recall that years ago. Good shout.

Just focus on the MWs being shed I suppose. The actual number for the stage is largely irrelevant.
 

sdrawk

Expert Member
Joined
Aug 19, 2008
Messages
1,242
New energy expert?

Let's just get to stage 7 first before triggering the public with a stage we might not even get.
Gotta have your stages in order. Can't just hop through stages like that. Need to make sure that every stage has been utilized.....

Bruh if 15000 MW needs to be shed then we hop to that stage (Stage 15), simple as that.
 

lkswan747

Expert Member
Joined
Jun 28, 2017
Messages
3,266
A stage at which a request for a meeting to discuss the meeting to discuss the energy crises is sent to the muppets, to which, the ministers issue a press statement confirming that an announcement will be made shortly.