Medupi and Kusile power stations will cost over R100 billion more
Besides the financial results themselves for Eskom’s financial year ending 31 March, perhaps the most important new information to come out at the media briefing at Megawatt Park on 5 July was Eskom’s latest estimate of the overnight capital costs, or cost to completion (CTC), for its Medupi and Kusile power stations.
The 4,764 MW Medupi coal-fired power station, situated near Lephalale in Limpopo province, has been under construction since 2007.
The 4,800 MW Kusile coal-fired power station close to Kendal power station in the Nkangala district of Mpumalanga province, has been under construction since 2008.
When questioned, Eskom’s head of capital projects, Mr. Abram Masango, advised that:
- The latest estimated CTC for Medupi, excluding flue gas desulphurization plant (FGD), and excluding interest during construction (IDC), had increased from R105 billion to R135 billion.
- The latest estimated CTC, including FGD, but excluding IDC, had increased from R118.5 billion to R160 billion.
The latest estimated interest during construction has still not been disclosed by Eskom.
However, in light of the significantly increased capital costs and delayed project programmes for both Medupi and Kusile (Fig. 1a and 1b), it is expected that IDC for both Medupi and Kusile could increase by about 25% above the figures previously indicated by Eskom in September 2014.
It should be noted that although FGD plant was not initially included in the costing of Medupi, the site has been designed to be ready to install FGD plant at the first major shutdown of each unit after construction.
Furthermore, FGD plant is required at both Medupi and Kusile in conditions of a US$3.75-billion World Bank loan to Eskom, approved in April 2010. Kusile, on the other hand, is being constructed including FGD plant from the start.
The history of the estimated CTC approved by the Eskom board from time to time and communicated to the public for the construction of Medupi is as follows:
- Apr 2007: R69.1 billion: Initial CTC for 6 units excluding FGD and IDC
- Sep 2008: R88.5 billion
- Sep 2009: R87.5 billion
- Jun 2011: R91.2 billion
- May 2013: R105 billion
- July 2016: R135 billion: Latest CTC excluding FGD and IDC
Similarly the CTC approved by the Eskom board for the construction of Kusile is as follows:
- Apr 2007: R80.6 billion: Initial CTC including FGD and excluding IDC
- May 2013: R118.5 billion
- July 2016: R160 billion: Latest CTC including FGD and excluding IDC
A previous estimated total CTC in September 2014 for Medupi and Kusile power stations, including IDC, FGD and the settling of unprocessed contractor claims, is given in Table 1.
An updated total CTC as at July 2016 for Medupi and Kusile power stations, including IDC, FGD and the settling of unprocessed contractor claims, is estimated in Table 2.
Item | Medupi | Kusile | Note |
Declared CTC as at May 2013 | R105-billion | R118.5-billion | Advised by Eskom May 2013 |
Flue gas desulphurisation | R15-billion | Included in declared CTC | Advised by Eskom Sep 2014 |
Interest during construction | R29.2-billion | R48.7-billion | Advised by Eskom Sep 2014 |
Settling of contractor claims | R5-billion | R5-billion | Estimate as at Sep 2014 |
Total CTC | R154.2-billion | R172.2-billion | Estimate as at Sep 2014 |
Table 1: Previous estimated total cost to completion (CTC) for Medupi and Kusile power station as at September 2014.
Item | Medupi | Kusile | Note |
Latest declared CTC | R135-billion | R160-billion | Advised by Eskom Jul 2016 |
Flue gas desulphurisation | R15-billion | Included in declared CTC | Advised by Eskom Sep 2014 |
Interest during construction | R40-billion | R60-billion | Estimate as at Jul 2016 |
Settling of contractor claims | R5-billion | R5-billion | Estimate as at Jul 2016 |
Total CTC | R195-billion | R225-billion | Estimate as at Jul 2016 |
Table 2: Latest estimated total cost to completion (CTC) for Medupi and Kusile power stations as at July 2016.
Thus the massive cost and time overruns at Eskom’s Medupi and Kusile power stations are expected further strain Eskom’s financial resources, and place upward pressure on Eskom’s electricity price trajectory in the years ahead.
Chris Yelland in the investigative editor at EE Publishers.
More on Eskom
Eskom staff need security teams when fixing power outage
Eskom’s Ingula Unit 1 synchronised
Former Eskom director found guilty of fraud, money laundering