Energy4.05.2022

Winter is coming and it looks bad for South Africa — load-shedding in 2022 vs 2021

While Eskom has implemented load-shedding on fewer days in 2022 than in 2021, the number of hours of rotational power cuts has been higher this year.

Eskom COO Jan Oberholzer provided the data in response to MyBroadband’s questions during a recent media briefing with updates.

Oberholzer said there were 29 days of load-shedding between January 2021 and April 2021, compared to 25 over the same period in 2022.

According to the CSIR, 2021 was the worst year of load-shedding when looking at the amount of power shed from the grid.

There were significantly more days of stage 2 load-shedding last year than 2022 — 27 compared to 17.

However, the most severe stage of load-shedding reached during this period last year was stage 3, which was only implemented on two days.

In 2022, Eskom has had to implement stage 4 for four days and two days of stage 3.

The table below compares the number of days and stages of load-shedding implemented from January to April in 2021 and 2022.

Load-shedding— 2022 vs 2021
Load-shedding stage and demand shed January 2021 to April 2021 January 2022 to April 2022
Stage 1 — 1,000MW 0 2
Stage 2 — 2,000MW 27 17
Stage 3 — 3,000MW 2 2
Stage 4 — 4,000MW 0 4
Total 29 25

Popular load-shedding app EskomSePush (ESP) also provided its data on load-shedding to MyBroadband.

Interestingly, this showed the full days of load-shedding had actually been slightly more this year than in 2021.

ESP co-founder Hermann Maritz said that in the first four months of the year, there had been nineteen 24-hour cycles of load-shedding in 2022, compared to seventeen in 2021.

At the same point in 2020, the country had suffered 23 full days of load-shedding.

The graph below shows how the full days of load-shedding climbed in 2020, 2021, and 2022.

With this week’s load-shedding yet to be counted, the 2022 line is expected to pass 2020 in early May.

If Eskom continues to implement load-shedding until Monday, 9 May 2022, at 05:00, it will add at least another five days.

That means Eskom would have reached 50% of the total days of load-shedding it implemented in 2021, with seven months and three weeks to go in 2022.

Maritz also pointed out a concerning trend ahead of the winter, when electricity demand typically increased.

In the previous two years, the country barely had load-shedding during April, while 2022 had eight days.

That indicates the system could be in a worse state than it was around the same time last year.

Eskom’s weekly system status report is further evidence of this, showing the energy availability factor (EAF) of its generating fleet for the year was 58.64%, compared to 61.79% in 2021.

The trend is particularly worrying considering that Eskom is heading into a period when it will significantly reduce scheduled maintenance.

Eskom uses the summer months with lower demand to take off around 5,000MW to 7,000MW of capacity for maintenance.

Oberholzer said this has already been reduced to 4,000MW and will be cut by a further 1,000MW in the coming weeks.

That is to ensure sufficient capacity is available for the winter when the system needs to be prepared for more radical demand fluctuations.

Oberholzer acknowledged it was impossible to give an accurate load-shedding outlook for the winter as the forecast could change quickly due to the system’s unreliability.

The chart below compares the full days of load-shedding in 2020, 2021, and 2022, with data provided by EskomSePush.


Now read: City Power’s fight against cable crime — R100 million spent in a year