Energy16.01.2024

New Eskom load-shedding stages coming soon

The National Energy Regulator of South Africa (Nersa) is expected to reveal changes to Eskom’s load-shedding stages in the coming weeks.

The regulator published a consultation document detailing a planned revised load-shedding approach that allows for up to stage 16 power cuts in August 2023.

The document, NRS 048-9 Electricity Supply – Quality of Supply: Code of Practice – Load reduction practices, system restoration practices, and critical load and essential load requirements under system emergencies, was opened for public comment on 11 August 2023.

The finalised NRS 048-9 Code of Practice Edition 3 will replace the current edition of the code Eskom’s System Operator uses to define load-shedding stages.

In addition to enabling the power utility to implement higher stages of power cuts, the draft document proposes allowing the System Operator to instruct distributors to reduce demand based on a percentage of the country’s national non-curtailment load at a given time.

The current rules only explicitly make provision for load-shedding up to stage 8.

If the revision proposed in the consultation document is approved in its current form, the System Operator will be able to instruct that electricity demand be dropped by between 5% and 80% of the total load, from stage 1 to stage 16.

The table below shows how much demand distributors or heavy electricity users will have to shave off their total load through load-shedding or load curtailment, respectively.

Proposed demand reductions under NRS 048-9 Electricity Supply Edition 3
Stage Reduction through load-shedding Reduction through load curtailment
1 5% of demand 10% reduction in normal demand profile
2 10% of demand 10% reduction in normal demand profile
3 15% of demand 15% reduction in normal demand profile
4 20% of demand 20% reduction in normal demand profile
5 25% of demand 30% reduction in normal demand profile
6 30% of demand 30% reduction in normal demand profile
7 35% of demand 40% reduction in normal demand profile
8 40% of demand 40% reduction in normal demand profile
9 45% of demand 50% reduction in normal demand profile
10 50% of demand 50% reduction in normal demand profile
11 55% of demand Reduction to essential loads or as instructed by System Operator
12 60% of demand Reduction to essential loads or as instructed by System Operator
13 65% of demand Reduction to essential loads or as instructed by System Operator
14 70% of demand Reduction to essential loads or as instructed by System Operator
15 75% of demand Reduction to essential loads or as instructed by System Operator
16 80% of demand Reduction to essential loads or as instructed by System Operator

MyBroadband asked Nersa for comment on when the new load-shedding rules will be finalised, but it did not provide feedback by the time of publication.

However, the regulator published an estimated timeline to complete the process alongside its original consultation paper.

It estimated that it would take 77 working days — or about four calendar months — to complete the approval of the document from the development of the consultation paper.

That period included nine working days before the publication of the consultation paper.

Based on these timelines, the regulator should have finalised the document sometime in December 2023.

In the absence of further notice from Nersa, it is reasonable to expect that the new rules should be published soon.

The screenshot below shows the timeline as set out in the consultation paper.

MyBroadband has calculated the megawatts that must be shed from the grid under the new stages of load-shedding under high-demand and low-demand scenarios.

The table below shows how much demand could theoretically be cut from demand under the proposed load-shedding stages.

Theoretical MW reductions under proposed load-shedding stages
Stage Low demand scenario:
23,000-24,000MW
High demand scenario:
30,000-32,000MW load
1 1,150–1,200MW 1,500–1,600MW
2 2,300–2,400MW 3,000–3,200MW
3 3,450–3,600MW 4,500–4,800MW
4 4,600–4,800MW 6,000–6,400MW
5 5,750–6,000MW 7,500–8,000MW
6 6,900MW–7,200MW 9,000–9,600MW
7 8,050–8,400MW 10,500–11,200MW
8 9,200–9,600MW 12,000–12,800MW
9 10,350–10,800MW 13,500–14,400MW
10 11,500–12,000MW 15,000–16,000MW
11 12,650–13,200MW 16,500–17,600MW
12 13,800–14,400MW 18,000–19,200MW
13 14,950–15,600MW 10,725–20,800MW
14 16,100–16,800MW 21,000–22,400MW
15 17,250–18,000MW 22,500–24,000MW
16 18,400–19,200MW 24,000–25,600MW
Show comments

Latest news

More news

Trending news

Sign up to the MyBroadband newsletter