Apologies for the confusion. I was referring to the opposite side where the previous company's server rack was located (Server Room). All the floor points remain intact with the keystones already in place. The only tasks left are to re-crimp all the cables in the server room and conduct testing...
Thanks for the reply - 110 cables needs RJ45 plugs put on and cable needs testing. For instance if we were getting someone to come out and do the above. What would be a reasonable price to charge for re-crimp 110 cables and test?
Thank you.
Howsit guys, hope all is well. Quick question. what would one charge if only one end of Cat cable needs to be re-crimped?
So the previous company that was in the building took all their patch panels out, leaving the cable. So only one end needs to be re-crimped
Thanks in advance for all the replies