Clear Choice Builders (CCB), the main contractor, which has pocketed more than R100-million from the project, was sent packing due to poor performance and delays.
MEC Sasekani Manzini acknowledged the delays while addressing the provincial legislature in Mbombela this week.
“We can report that eThandukukhanya CHC was planned for completion on the 30th of September 2024. However, the national department has terminated the service of the contractor due to poor performance and failure to bring the project to completion,” Manzini said.
CCB managing director Sipho Manonga did not respond to inquiries on the matter.
Sunday World has learnt that this is not CCB’s first troubled project.
In Soweto, the Nancefield Primary School renovation project remains incomplete after five years, forcing pupils into mobile classrooms while costs surged beyond the R120-million budget.
The company was dismissed from the project in 2022 for what Gauteng Department of Infrastructure Development spokesperson Bongiwe Gambu labelled at the time as “non-
performance”.
CCB also faced delays and payment disputes in a R168-million project to rebuild Rivoni School for the Blind in Limpopo.
https://sundayworld.co.za/news/rogue-contractor-fired-over-delayed-r218m-clinic-project/