We finally want to pull the trigger & go Solar

@wingnut771

Hypothetically, I would. I would also hypothetically make sure that the excess solar sell-back is quite low, in order not to hypothetically trigger any hypothetical inspections.

Prepaid or postpaid?
So would I but when I questioned AI if my meter could do it with the pics I provided it, it came back and told me these dbn ones have a lock to prevent it from turning backwards. This new info definitely put a spanner into my hypothetical plans.
 
@wingnut771

Hypothetically, I would. I would also hypothetically make sure that the excess solar sell-back is quite low, in order not to hypothetically trigger any hypothetical inspections.

Prepaid or postpaid?
For arguments sake let's assume it's post paid with a mechanical meter that's at least 30 years old.
 
Hi everyone! Congrats @bwana on your install and I hope it's going to be a seamless one!

Wanted to get some advice regarding a quote received for the following system all VAT INCL:
12x Trina bifacial 635W Panels = R22k (20yr warranty)
1x SOLAX X1-RENO 8kw Inverter = R24.5k (10yr warranty)
1x Helio 16kwh Li-iron battery = R35k (10yr warranty)
PV mounting + Cable + Conduit = R18k
Solar DC-DB PV Combiner = R3.9k
AC DB Single Phase = R5k
AC cabling = R4.7k (+-55m)
Battery consumables = R3.4k (fuses/holders/cables/lugs)
Other Consumables = R2.4k
DB Board Split = R1.8k
Solar Installation + CoC = R18k
Travel costs (Jhb -> Pretoria) = R3.8k
TOTAL = R142.5k

I average around 750-950kwh per month (solar geyser installed and pool pump) and also have 4 additional older 550W Trina panels already installed - missus and I work from home permanently and my work items run around +-850w constant +-12-14hours weekdays

Have been fighting City of Tshwane on a billing dispute for months and just getting really gatvol of them switching us off willy nilly during the dispute process

The additional items like DB + consumables etc does sound a bit expensive but my DB is a long ways away from the inverter installation and current DB does need reworking

Let me know what you think!
 
For arguments sake let's assume it's post paid with a mechanical meter that's at least 30 years old.
all I am saying :thumbsup: because of"test"I did for few months
 
The arrow on mine means it only turns that direction:
View attachment 1949143
The electrician doing my installation seems pretty confident that the arrow indicates the direction the wheel is supposed to turn when power is consumed, not that it's the only direction it can turn.
 
mine had that same arrow, it did nothing xd

The electrician doing my installation seems pretty confident that the arrow indicates the direction the wheel is supposed to turn when power is consumed, not that it's the only direction it can turn.
That's encouraging. iirc, there were other details on the meter, think it was this 20/80A that AI also pointed to confirming that there is a limit feeding backwards of 20A and could damage the meter if more was pushed but I also remember it saying there is a mechanical lock. Then again, we all know how stupid AI is.
1793277426790.png
 
Night is 14 average and day is 13.
Yeah, then I think you're better off getting slightly more battery capacity. You're supposed to discharge max 80%, which means you're only going to cover about 7kwh of your night time use. If you're a bit more conservative like me, I prefer to only discharge to around 40% in case of a power outage.

I think if you up your capacity to around 15kwh, you'd cover most of your night time usage. On most days, you should more than cover your day usage and charge your batteries.

I have 16 x 600w panels. During summer, my battery is full and my geyser is heated up around 11h00. In winter, I can produce around 45kwh if I use alot of heating appliances.

My next task is to get another battery for peace of mind.
 
Hi everyone! Congrats @bwana on your install and I hope it's going to be a seamless one!

Wanted to get some advice regarding a quote received for the following system all VAT INCL:
12x Trina bifacial 635W Panels = R22k (20yr warranty)
1x SOLAX X1-RENO 8kw Inverter = R24.5k (10yr warranty)
1x Helio 16kwh Li-iron battery = R35k (10yr warranty)
PV mounting + Cable + Conduit = R18k
Solar DC-DB PV Combiner = R3.9k
AC DB Single Phase = R5k
AC cabling = R4.7k (+-55m)
Battery consumables = R3.4k (fuses/holders/cables/lugs)
Other Consumables = R2.4k
DB Board Split = R1.8k
Solar Installation + CoC = R18k
Travel costs (Jhb -> Pretoria) = R3.8k
TOTAL = R142.5k

I average around 750-950kwh per month (solar geyser installed and pool pump) and also have 4 additional older 550W Trina panels already installed - missus and I work from home permanently and my work items run around +-850w constant +-12-14hours weekdays

Have been fighting City of Tshwane on a billing dispute for months and just getting really gatvol of them switching us off willy nilly during the dispute process

The additional items like DB + consumables etc does sound a bit expensive but my DB is a long ways away from the inverter installation and current DB does need reworking

Let me know what you think!
24k for an 8kw inverter?? Never even heard of that brand either.
 
Hi everyone! Congrats @bwana on your install and I hope it's going to be a seamless one!

Wanted to get some advice regarding a quote received for the following system all VAT INCL:
12x Trina bifacial 635W Panels = R22k (20yr warranty)
1x SOLAX X1-RENO 8kw Inverter = R24.5k (10yr warranty)
1x Helio 16kwh Li-iron battery = R35k (10yr warranty)
PV mounting + Cable + Conduit = R18k
Solar DC-DB PV Combiner = R3.9k
AC DB Single Phase = R5k
AC cabling = R4.7k (+-55m)
Battery consumables = R3.4k (fuses/holders/cables/lugs)
Other Consumables = R2.4k
DB Board Split = R1.8k
Solar Installation + CoC = R18k
Travel costs (Jhb -> Pretoria) = R3.8k
TOTAL = R142.5k

I average around 750-950kwh per month (solar geyser installed and pool pump) and also have 4 additional older 550W Trina panels already installed - missus and I work from home permanently and my work items run around +-850w constant +-12-14hours weekdays

Have been fighting City of Tshwane on a billing dispute for months and just getting really gatvol of them switching us off willy nilly during the dispute process

The additional items like DB + consumables etc does sound a bit expensive but my DB is a long ways away from the inverter installation and current DB does need reworking

Let me know what you think!
1x Helio 16kwh Li-iron battery = R35k (10yr warranty) ?:unsure:
Travel costs (Jhb -> Pretoria) = R3.8k :eek: I know fuel is expensive, but, DAMN!

Here is a fuel cost estimate as seen on the TopAuto website: https://topauto.co.za/features/166079/what-it-costs-to-drive-from-pretoria-to-joburg-every-day/

Below is a breakdown of what the average motorist commuting between Johannesburg and Pretoria every day can expect to spend on petrol and diesel, depending on their vehicle’s fuel efficiency.

Petrol 95​

Fuel efficiencyFuel neededMonthly spend
5.0l/100km120 litresR3,630.00
6.0l/100km144 litresR4,356.00
7.0l/100km168 litresR5,082.00
8.0l/100km192 litresR5,808.00
9.0l/100km216 litresR6,534.00
10.0l/100km240 litresR7,260.00

Diesel 50ppm​

Fuel efficiencyFuel neededMonthly spend
5.0l/100km120 litresR3,994.80
6.0l/100km144 litresR4,793.76
7.0l/100km168 litresR5,592.72
8.0l/100km192 litresR6,391.68
9.0l/100km216 litresR7,190.64
10.0l/100km240 litresR7,989.60
 
Hi everyone! Congrats @bwana on your install and I hope it's going to be a seamless one!

Wanted to get some advice regarding a quote received for the following system all VAT INCL:
12x Trina bifacial 635W Panels = R22k (20yr warranty)
1x SOLAX X1-RENO 8kw Inverter = R24.5k (10yr warranty)
1x Helio 16kwh Li-iron battery = R35k (10yr warranty)
PV mounting + Cable + Conduit = R18k
Solar DC-DB PV Combiner = R3.9k
AC DB Single Phase = R5k
AC cabling = R4.7k (+-55m)
Battery consumables = R3.4k (fuses/holders/cables/lugs)
Other Consumables = R2.4k
DB Board Split = R1.8k
Solar Installation + CoC = R18k
Travel costs (Jhb -> Pretoria) = R3.8k
TOTAL = R142.5k

I average around 750-950kwh per month (solar geyser installed and pool pump) and also have 4 additional older 550W Trina panels already installed - missus and I work from home permanently and my work items run around +-850w constant +-12-14hours weekdays

Have been fighting City of Tshwane on a billing dispute for months and just getting really gatvol of them switching us off willy nilly during the dispute process

The additional items like DB + consumables etc does sound a bit expensive but my DB is a long ways away from the inverter installation and current DB does need reworking

Let me know what you think!
Here is a breakdown of our install done in March of this year. Total cost R130458.
1793282494197.png
 
24k for an 8kw inverter?? Never even heard of that brand either.
Yep know more expensive than Deye/Sunsynk and this specific model is (apparently) brand new to SA

From my research, Solax are a very well known and trusted brand in Europe
 
Here is a breakdown of our install done in March of this year. Total cost R130458.
View attachment 1949170
Thanks for that

Install estimated to take +-3-4days they said so I can kind of excuse the fuel cost

What bothers me is the cost of the various things below:

R5000 for PV mounting structure earthing and bonding
R1800 for splitting main house DB
R3500 Battery consumables -> shouldn't cables and lugs come with the battery?
R5000 for a standard DB with change over switch
R2400 for extra consumables: trunking/flex conduit/heat shrink/fischer plugs etc

seems a bit on the high side...
 
The last of today's sunshine is charging batteries. Tomorrow we'll be tied into the house.
Is that roof open to the elements ? right-hand side of the photo
How warm does that room get ? so close to the ceiling heat is going to be trapped, bit concerned inverter may not like temp.
 