South Africa’s first new nuclear reactors could be online by 2036

Are you people nuts?

It took nearly 17 years to build Kusile. A coal fired power station using established tried and testing technology that Eskom had decades of experience with.

You think they'll build a nuclear power station in just 20 years?

My eldest is 7 at the moment. Maybe if her children live healthy lives, and some new technologies show up to help extend human lives, they might live long enough to see this thing reach 20% completion.
Wishing that I see it in my lifetime.... yeah I'm probably nuts.
 
Let's say it together.

KUSILE

Fresh delays at Medupi and Kusile amid eye-watering costs ...

Construction on Eskom's Kusile Power Station began in August 2008 with an initial target for full 4,800 MW completion around 2014–2017, but the project suffered over a decade of delays and reached full commercial operation of all six units in September 2025. [1, 2, 3]

Timeline of Delays and Milestones
    • 2008: Construction officially kicks off near Delmas and Witbank (Mpumalanga) with an original projected completion timeline of roughly 6 years (targeting 2014–2017). [1, 2, 3]
    • 2014–2017: Initial commercial operational target dates for Unit 1 and subsequent units slip repeatedly due to contractor challenges and design adjustments. [1, 2]
    • May 2017: Unit 1 achieves commercial operation. [1]
    • October 2020: Unit 2 achieves commercial operation. [1]
    • June 2022: Unit 4 achieves commercial operation. [1]
    • Late 2022 / 2023: Progress is further hindered by technical and mechanical setbacks, including a gas air heater fire on Unit 5. [1]
    • September 29, 2025: Unit 6 officially enters commercial operation, marking the completion of all six units (4,800 MW) and concluding Eskom's major build program. [1, 2]
    • 2026: Final close-out and auxiliary project works continue, with overall project costs and extended close-out timelines stretching past R200 billion compared to the original R121 billion budget. [1, 2]
Main Causes of Delays
    • Design & Technical Flaws: Issues with boiler designs (requiring major contractor changes like replacing Hitachi with Mitsubishi), milling plant defects, flue gas ducting erosion, and control and instrumentation (C&I) contract terminations (replacing Alstom with ABB). [1, 2, 3]
    • Contractor & Labor Issues: Poor contractor performance, widespread site-access delays, and frequent labor unrest/strikes over wages. [1, 2, 3]
    • State Capture & Corruption: Extensive corruption and kickback schemes—highlighted during the Zondo Commission—including irregularities involving contracts with ABB South Africa, which later admitted fault and repaid billions. [1, 2, 3]




MEDUPI

The real reasons Medupi and Kusile were delayed — and did ...

The Medupi Power Station project commenced construction in 2007 with an initial target completion date of 2012, but suffered more than nine years of delays, achieving full construction completion only in 2021. [1]

Chronological Timeline & Milestones
    • 2007: Construction officially begins near Lephalale, Limpopo, with a 4- to 5-year timeline planned. [1, 2]
    • 2012–2015: Missed initial deadlines; the first unit (Unit 6) was synchronized to the national grid in March 2015. [1]
    • 2019: Revised full-plant completion target passed without finishing all six units. [1]
    • 2021 (July/August): Commercial operation achieved for the plant, followed abruptly on August 9, 2021 by a severe hydrogen explosion in Unit 4, which knocked 700–800 MW offline and required multi-year repairs. [1, 2]
    • 2024–2025: Unit 4 repairs progressed through replacement generator sourcing and return-to-service milestones, eventually restoring Unit 4 to the grid. [1, 2]
    • 2026: Ancillary environmental upgrades, such as the Flue Gas Desulphurisation (FGD) system required for emissions control, remain delayed with completion targeted around 2030. [1]
Key Causes of Delays
    • Labor Unrest and Strikes: Repeated violent strikes, worker displacement, and protracted labor stoppages between 2012 and 2015 caused up to nine months of lost production. [1, 2]
    • Technical and Design Defects: Persistent issues with control and instrumentation systems, boiler welding failures requiring thousands of re-welds, steam piping pressure problems, and ash system blockages. [1, 2]
    • Contract Management Issues: Fragmented, multi-contract approaches instead of turnkey solutions, alongside poor contractor management. [1, 2]
    • Unit 4 Explosion Setback: A catastrophic hydrogen explosion in 2021 sidelined Unit 4 for years, adding fresh recovery timelines and high repair costs. [1, 2]
 
Let's say it together.

KUSILE

View attachment 1953001

Construction on Eskom's Kusile Power Station began in August 2008 with an initial target for full 4,800 MW completion around 2014–2017, but the project suffered over a decade of delays and reached full commercial operation of all six units in September 2025. [1, 2, 3]

Timeline of Delays and Milestones
    • 2008: Construction officially kicks off near Delmas and Witbank (Mpumalanga) with an original projected completion timeline of roughly 6 years (targeting 2014–2017). [1, 2, 3]
    • 2014–2017: Initial commercial operational target dates for Unit 1 and subsequent units slip repeatedly due to contractor challenges and design adjustments. [1, 2]
    • May 2017: Unit 1 achieves commercial operation. [1]
    • October 2020: Unit 2 achieves commercial operation. [1]
    • June 2022: Unit 4 achieves commercial operation. [1]
    • Late 2022 / 2023: Progress is further hindered by technical and mechanical setbacks, including a gas air heater fire on Unit 5. [1]
    • September 29, 2025: Unit 6 officially enters commercial operation, marking the completion of all six units (4,800 MW) and concluding Eskom's major build program. [1, 2]
    • 2026: Final close-out and auxiliary project works continue, with overall project costs and extended close-out timelines stretching past R200 billion compared to the original R121 billion budget. [1, 2]
Main Causes of Delays
    • Design & Technical Flaws: Issues with boiler designs (requiring major contractor changes like replacing Hitachi with Mitsubishi), milling plant defects, flue gas ducting erosion, and control and instrumentation (C&I) contract terminations (replacing Alstom with ABB). [1, 2, 3]
    • Contractor & Labor Issues: Poor contractor performance, widespread site-access delays, and frequent labor unrest/strikes over wages. [1, 2, 3]
    • State Capture & Corruption: Extensive corruption and kickback schemes—highlighted during the Zondo Commission—including irregularities involving contracts with ABB South Africa, which later admitted fault and repaid billions. [1, 2, 3]




MEDUPI

View attachment 1952999

The Medupi Power Station project commenced construction in 2007 with an initial target completion date of 2012, but suffered more than nine years of delays, achieving full construction completion only in 2021. [1]

Chronological Timeline & Milestones
    • 2007: Construction officially begins near Lephalale, Limpopo, with a 4- to 5-year timeline planned. [1, 2]
    • 2012–2015: Missed initial deadlines; the first unit (Unit 6) was synchronized to the national grid in March 2015. [1]
    • 2019: Revised full-plant completion target passed without finishing all six units. [1]
    • 2021 (July/August): Commercial operation achieved for the plant, followed abruptly on August 9, 2021 by a severe hydrogen explosion in Unit 4, which knocked 700–800 MW offline and required multi-year repairs. [1, 2]
    • 2024–2025: Unit 4 repairs progressed through replacement generator sourcing and return-to-service milestones, eventually restoring Unit 4 to the grid. [1, 2]
    • 2026: Ancillary environmental upgrades, such as the Flue Gas Desulphurisation (FGD) system required for emissions control, remain delayed with completion targeted around 2030. [1]
Key Causes of Delays
    • Labor Unrest and Strikes: Repeated violent strikes, worker displacement, and protracted labor stoppages between 2012 and 2015 caused up to nine months of lost production. [1, 2]
    • Technical and Design Defects: Persistent issues with control and instrumentation systems, boiler welding failures requiring thousands of re-welds, steam piping pressure problems, and ash system blockages. [1, 2]
    • Contract Management Issues: Fragmented, multi-contract approaches instead of turnkey solutions, alongside poor contractor management. [1, 2]
    • Unit 4 Explosion Setback: A catastrophic hydrogen explosion in 2021 sidelined Unit 4 for years, adding fresh recovery timelines and high repair costs. [1, 2]
1794326709732.png
 
Energy minister Kgosientsho Ramokgopa has set out how government will take its 5.2GW nuclear build programme to market – and has dared opponents to try to stop it, saying the evidence for nuclear is settled.

Damn straight its settled. Everyone knows its too expensive, takes too long to build, and other generation is cheaper.

"New nuclear power has a higher levelized cost of electricity (LCOE) compared to solar PV and onshore wind."

Advanced Nuclear: Estimated around $110/MWh (and forecasted to remain steady through 2050
Utility-Scale Solar PV: Estimated around $55/MWh in 2023, with projections dropping down to $25/MWh by 2050. Capital costs run under $1,000 per kW.
Onshore Wind: Estimated around $40/MWh in 2023, expected to decline to $35/MWh by 2050.

Nuclear takes 20+ years to build. Can't use it while its in construction, and you're eating finance costs for the first 20 years before you generate a rand of power. Solar or wind - can be generating during construction. Most PV or Wind plants ready within a year, or sooner.


You know when they want Nuclear, its because of the feeding trough thats coming. The ANC already made $$$ from Medupi, they'll stand to make far, far more from Nuclear.

Want to bankrupt the country, and make some black "entrepreneurs" rich? Go Nuclear.
 
Damn straight its settled. Everyone knows its too expensive, takes too long to build, and other generation is cheaper.

"New nuclear power has a higher levelized cost of electricity (LCOE) compared to solar PV and onshore wind."

Advanced Nuclear: Estimated around $110/MWh (and forecasted to remain steady through 2050
Utility-Scale Solar PV: Estimated around $55/MWh in 2023, with projections dropping down to $25/MWh by 2050. Capital costs run under $1,000 per kW.
Onshore Wind: Estimated around $40/MWh in 2023, expected to decline to $35/MWh by 2050.

Nuclear takes 20+ years to build. Can't use it while its in construction, and you're eating finance costs for the first 20 years before you generate a rand of power. Solar or wind - can be generating during construction. Most PV or Wind plants ready within a year, or sooner.


You know when they want Nuclear, its because of the feeding trough thats coming. The ANC already made $$$ from Medupi, they'll stand to make far, far more from Nuclear.

Want to bankrupt the country, and make some black "entrepreneurs" rich? Go Nuclear.
1794330470288.png
1794330593695.png
1794331104823.png1794331167918.png1794331182241.png1794331192486.png1794331201769.png
 
Damn straight its settled. Everyone knows its too expensive, takes too long to build, and other generation is cheaper.

"New nuclear power has a higher levelized cost of electricity (LCOE) compared to solar PV and onshore wind."

Advanced Nuclear: Estimated around $110/MWh (and forecasted to remain steady through 2050
Utility-Scale Solar PV: Estimated around $55/MWh in 2023, with projections dropping down to $25/MWh by 2050. Capital costs run under $1,000 per kW.
Onshore Wind: Estimated around $40/MWh in 2023, expected to decline to $35/MWh by 2050.

Nuclear takes 20+ years to build. Can't use it while its in construction, and you're eating finance costs for the first 20 years before you generate a rand of power. Solar or wind - can be generating during construction. Most PV or Wind plants ready within a year, or sooner.


You know when they want Nuclear, its because of the feeding trough thats coming. The ANC already made $$$ from Medupi, they'll stand to make far, far more from Nuclear.

Want to bankrupt the country, and make some black "entrepreneurs" rich? Go Nuclear.
Nuclear is just more stable and always on.

The solar and wind cost estimates doesn't account for a week of storage when the sun doesn't shine.

This debate has been had to death and in the real world renewables fail all the time. I am all for it but you need baseload real power.
 