I partially agree, but the problem is two-fold.
1) Eskom processes, although dictated by their 22-month turnaround from approval to commissioning on any project, their inter-departmental processes is clogged with red tape in the form of KPI's. No department will help another if they don't get measured on it. Effectively giving each other the finger when help is required.
2) The Department of Energy had issued bidding rounds for IPPs. So Eskom reacted where they could, then halfway through, the DoE approves more and more IPPs willy nilly...placing further strain on Eskom's already in-the-pipeline designs, resetting the whole thing. As much as we all love to hate Eskom, this is kind of a dick move and not an easy one for Eskom to solve. How do you build more and bigger lines if you don't have a servitude or funds to do so? Localising IPPs would be the best option.
(No I don't work for Eskom, but reading published magz like Watts On and such will reveal all this info)
...