How long? Any advice?

Chad Rocks

Member
Joined
Aug 4, 2020
Messages
20
Reaction score
0
Hi guys, how long does the process take after a Detailed Site Plan has been signed off for a complex? The FNO is Octotel.

Anyone?

Thanks in advance.
 
I can't comment on Octotel, but if there is no need for a wayleave, the build usually starts within 2 weeks of MDU sign off for us.
 
Hey thanks for replies.

What's a wayleave?
Permission from council to work in the public space like the road reserve (pavement) or do a road crossing. If the work is completely within your MDU, there will be no need for one, however, there might be need for one to connect your complex to the network in the street.

From our perspective, sometimes we will build the MDU whilst we wait on the wayleave for the external build, sometimes not, it depends on the complexity of the build. Again, this is our process, I can't speak for Octotel.
 