Eskom delays Koeberg unit return-to-service

Eskom has revealed that Koeberg's Unit 2 generator will only return to service by the end of July 2022, after previously confirming that it was set for the middle of the month.

The power utility's chief operating officer Jan Oberholzer attributed the delays to unexpected issues with the unit's polar crane, which it has now resolved.
 

dualmeister

Honorary Master
Joined
Oct 15, 2005
Messages
51,374
Once the generating unit has been ramped up successfully, it will add 920MW to the national power grid.
I read earlier that Koeberg was originally built to supply the Western Cape with power :laugh:

Wikipedia
 

Kola-CT

Expert Member
Joined
Jun 5, 2022
Messages
1,345
I was told by a person on the project last week that they have been delayed for at least 50 days, July and August must be very long months then...
 

r00igev@@r

Honorary Master
Joined
Dec 14, 2009
Messages
12,105
Its Jan's fault. That bliksem stuffs up everything. I'm talking about Oberholzer and not van Riebeeck!
 