@Pho3nix
Rereading your OP, I suspect that you made a typo - you have a 5 kW Deye inverter, not a 5 kW Deye battery? The Deye can push power back to your non-essential loads.
If so, do you know if the installers installed a CT around the live cable going to the main breaker in your DB? It is basically a plastic thing that clamps around the cable, with a wire (thin, usually black and white) running back to your inverter.
If there is a CT, then only your inverter configuration needs to be updated to push excess solar power to your non-essential loads. I have configured several Sunsynk inverters, but no Deye inverters yet, so I'm not 100 % sure what the Deye / Solarman alternative to the Sunsynk option is. I think it is "Zero Export to CT" in the System Work Mode. On Sunsynk the inverter won't push battery power to the non-essential loads, but you may need to set the minimum battery level in the time of use settings (System Work Mode 2) to make sure that it doesn't deplete your battery into the geyser.

Once your CT is working correctly, your excess solar capacity will go to the geyser or oven (without rewiring the geyser or oven).
Do you have a timer on your geyser? If you can set the geyser to start heating up at 12h30, then once your battery is full the solar capacity will go to the geyser. That will give your some saving (not much, I expect ~1.5 kWh per day). But we can then see how much your geyser use daily and try to calculate potential savings if you were to put in a smaller element or install additional panels.
Then you get quotes for the additional panels, and calculate if there will be an ROI before you move.
Rereading your OP, I suspect that you made a typo - you have a 5 kW Deye inverter, not a 5 kW Deye battery? The Deye can push power back to your non-essential loads.
If so, do you know if the installers installed a CT around the live cable going to the main breaker in your DB? It is basically a plastic thing that clamps around the cable, with a wire (thin, usually black and white) running back to your inverter.
If there is a CT, then only your inverter configuration needs to be updated to push excess solar power to your non-essential loads. I have configured several Sunsynk inverters, but no Deye inverters yet, so I'm not 100 % sure what the Deye / Solarman alternative to the Sunsynk option is. I think it is "Zero Export to CT" in the System Work Mode. On Sunsynk the inverter won't push battery power to the non-essential loads, but you may need to set the minimum battery level in the time of use settings (System Work Mode 2) to make sure that it doesn't deplete your battery into the geyser.

Once your CT is working correctly, your excess solar capacity will go to the geyser or oven (without rewiring the geyser or oven).
Do you have a timer on your geyser? If you can set the geyser to start heating up at 12h30, then once your battery is full the solar capacity will go to the geyser. That will give your some saving (not much, I expect ~1.5 kWh per day). But we can then see how much your geyser use daily and try to calculate potential savings if you were to put in a smaller element or install additional panels.
Then you get quotes for the additional panels, and calculate if there will be an ROI before you move.