So they got an SSEG certificate and then it was revoked? There is a clause for this but not sure if thats what you mean:One of my customers registered their system in 2023. I supplied a COC. A MECER 5kW inverter was used, supplied by VOLTEX
In Feb 2026 CoCT fitted a new electric meter. Their tech declared the installation invalid as a MECER is not approved. VOLTEX said it was. In May a R7000 fine was added to their rates account. Now VOLTEX were not interested
R16000 for a SunSynk inverter. VOLTEX are providing several excuses why their inverter was declared invalid and will not accept liability
13.2 The City reserves the right to (not unreasonably) alter its requirements for whatsoever reason and the customer will be obliged to ensure at the customer's cost that the SSEG equipment complies with the additional requirements.