Former Eskom employee turned contract arrested for making R14.7 million payment to company that never delivered
A former Eskom employee turned contractor was arrested this past week for making an unauthorised R14.7 million payment from the utility's accounts to a dubious supplier that never...
Eskom increases load-shedding until further notice
Eskom has announced stage 4 load-shedding until further notice.
This is due to the breakdowns of a generating unit each at Koeberg, Medupi, Kriel, Arnot and Lethabo power stations.
Eskom announces load-shedding plans for the week — here is the timetable
Eskom has announced that it will continue running stage 4 rotational power cuts during evening peaks and early mornings, with stage 3 during daylight hours.
“Stage 4 load-shedding will continue to be implemented at 16:00...
Eskom warns of load-shedding at short notice as six units break down
Eskom has warned that it may need to implement stage 2 load-shedding at short notice on Monday evening between 18:00 and midnight due to a shortage of generation capacity.
The state-owned power utility has suffered breakdowns...