The time has come to ditch some of my household's dependance on Eskom. Order placed with the installer last week and if all goes well, they should be starting the install tomorrow.

Here is the kit being used:

1 x Sunsynk 5.5kW Inverter
1 x Sunsynk 5.12kWh Battery
10 x JA Solar 545W Panels (this might change due to stock levels)

All plugs and lights in the main house will go on the essential load, plus some plugs and lights in a wendyhouse on my property. Geysers, jacuzzi, irrigation, large air-con, stove and flat will go on non-essential load.

Will post some photos as soon as possible.
 
Last edited:
That's a short wait... location and installer ?
 
is that a good price ?

also is that including everything ..the certificate or some sort with the city as well
Includes everything. The COC certificate is included as well. I believe I will have to register with the CoCT myself afterwards.
 
Congrats Dawie. Today is the day that your life will change for the better.

Welcome to the club
 
The time has come to ditch some of my household's dependance on Eskom. Order place with the installer last week and if all goes well, they should be starting the install tomorrow.

Here is the kit being used:

1 x Sunsynk 5.5kW Inverter
1 x Sunsynk 5.12kWh Battery
10 x JA Solar 545W Panels (this might change due to stock levels)

All plugs and lights in the main house will go on the essential load, plus some plugs and lights in a wendyhouse on my property. Geysers, jacuzzi, irrigation, large air-con, stove and flatlet will go on non-essential load.

Will post some photos as soon as possible.
Nice.

I have a 7 week wait for mine.

5 weeks to go.
 