Cape Town - A Parliamentary written reply given by Transport Minister Sbu Ndebele to Don Gumede of the ANC shows that the transport network being prepared for the Soccer World Cup in Cape Town is a long way from being ready for the event.

According to the reply circulated on Tuesday, bus-based park and ride facilities which were supposed to have been competed in October this year are still only 43% complete.

A city-wide non-motorised transport plan involving a number of upgrades to the pedestrian and bicycle network in the CBD and the Somerset Road areas was supposed to have been finished in August. The project is currently 28% completed.

A project aimed at keeping pedestrians separated from the traffic on the Western Boulevard had a planned completion date of October. It is currently 71% completed.

Pedestrian improvements worth R55m at Green Point stadium have only been 59% completed although the planned completion date was November this year.

An integrated fare management system which was to be one of the key components of the public transport improvement programme for the province is currently standing at 15% completeness with a planned completion date of 30 October 2009.

A non-motorised transport bridge to Bhunga Avenue over the N2, as well as NMT links between Langa and the Klipfontein Corridor/Athlone Stadium were planned for completion on 15 October. The project is only 74% complete.

The city has embarked on intelligent transport management system (ITS) to improve network operations on a city-wide basis. The planned completion date was 31 January 2009, but the project is currently only 32% completed.

Other cities are also having problems, but many of the projects in Gauteng are pretty much on time and 100% complete.

I thought everything was going according to plan.

The article gives no information as to why everything is so far from completiion - 15 % completed, due date 2 months ago ?
:o
 
Its one of those articles which is so general it could mean anything.

It makes no mention of the extra money spent to accelerate many projects, some of which were only meant for completion post 2010.

In addition CT generally sets realistic targets. Not targets that are meant to please people.

e.g. CT stadiums target was end Feb 2010, accelerated to December 2009, while other stadia all provided willy nilly May -October 2009 targets, but are still busy completing the venues.
 
Transport Projects Update: 9 October 2009

PTIS 1: ITS


  • N1 CCTV: On schedule - February 2010
  • N2 Remote Monitoring: Complete
  • MTI Call Centre: Complete, in operation
PTIS 2: Project 2 - Airport to City road link

Hospital Bend

  • 75% complete
  • Funding: R13 million shortage (repairs to existing structure and resurfacing of existing roads to be omitted if funding not sourced)
N2 Outbound

  • 69% complete
  • Completion : End December 2009
N2 Bus Lane Inbound: Complete and in operation

PTIS 2: Project 3 - Klipfontein Corridor NMT Projects

Projects completed:

  • Bosduif/Petunia, Athlone Phase 1
  • Mowbray Liesbeek Parkway Phase 1
  • Spine Road Khayelitsha Phase 1
  • Hazel Road, Athlone
  • NY1 NMT Link Phase 2
  • Access to Red Cross Hospital
  • Spine Road Khayelitsha Phase 2
  • Bosduif/Petunia, Athlone Phase 2
Projects under construction:


  • Ingulube-Emms Drive: 40%
  • NY1 NMT Link Phase 2: 60%
  • Mowbray Liesbeek Parkway Phase 2: 55%
  • Big Lotus River: 50%
  • Nolungile Station: 15%
  • Nonqubela Station: 20%
PTIS 2 Granger Bay Boulevard


  • 70% complete
  • Opening, early December 2009
  • Funding: R18 million shortfall
  • Completion: February 2010
PTIS 2 CTIA IRT Project


  • Platform structure ahead of schedule, Target December 2009
  • Station structure: April 2010 Completion Target
PTIS 3 - Park and Ride (Rail based)


  • Kuils River Station: Ahead of schedule, February 2010
  • Monte Vista Station: Ahead of schedule, February 2010 (Work yet to start)
  • Brackenfell Station: On schedule, March 2010
  • Kraaifontein Station: On schedule, March 2010 (Work yet to start)
  • Ottery Station: April 2010 completion (Work yet to start)
  • Retreat Station: April 2010 completion (Work yet to start)
  • Landsdowne Station: Funding required
  • Fish Hoek Station: Funding required
  • Oosterzee Station: Funding required
  • Eerste Rivier Station: Funding required
PTIS 3 - Long Distance Bus Terminal


  • Work yet to start. Delays with PRASA
  • Tender evaluation in progress
  • May 2010 completion achievable
PTIS 3 - NMT Bridge Bhunga Avenue


  • All concrete works completed. Precast decks to be lifted end October
  • Cycle tracks: Ramps complete
  • Vygieskraal & Cornflower Culvert: Completion November 2009
  • Landscaping: 95% complete
  • Steel elements: November 2009
PTIS 3 - Road Signage Upgrade


  • M3, M5: Delays
  • M6, M7: Complete
  • M4: Behind schedule, November 2009 completion
  • R27, N1, N2: Underway
  • M62: Tender Awarded
  • CBD Signage: Tender closed
  • CBD and Stadium Event Signs: Tender to be awarded December 2009
PTIS 3 - Pedestrian Improvement: Stadium to CBD


  • Somerset Road to Ebenezer Road: End December 2009 completion
  • Ebenezer to Buitengracht: April 2010
  • Ebenezer realignment/works: Delayed
  • Somerset Pavement Widening: Heritage Complications
PTIS 3 - Pedestrian Improvement: Bridges


  • Buitengracht Bridge: 60% complete, February 2010 completion
  • Steel structure on site
  • Structure up by final draw but not operational
  • Waterkant Bridge: February 2010 completion
  • Waterkant Fan Walk NMT: Slightly behind schedule
PTIS 3 Koeberg Interchange


  • 50% complete
  • Ramp A completion date, April 2010
  • Roadworks: 65%
  • Ramp A: 51%
  • Ramp B: 41%
  • M5 viaduct: 34%
PTIS 3 Table Bay Boulevard


  • 56% complete
  • May 2010 completion
  • Lighting : January 2010
General IRT Works

Ahead of schedule in some areas.

  • Inner City Depot: Behind schedule
  • Negotiations with Transnet underway
  • Tenders Awarded for Inner City IRT Works from Hertzog Boulevard to Western Boulevard
  • Feeder stops have been verified
  • Hertzog Boulevard Station and Bus Way: May 2010
 
If we're talking about delays, the real concern would be the Long Distance bus terminal which due to funding issues has only started works this month.

The IRT project of course remains critical but the stations structures are going up already and the red lanes are being prepared.

The city even paid extra to accelerate the Green Point station to February/March 2010.

Heritage issues delayed the paving of the Fan Walk in some areas but again not critical since this project is proceeding well and will serve the city for decades to come.

The airport is basically complete except for roadworks.

The N1 roadworks were accelerated to May 2010 to avoid further congestion.

Phase1 of Koeberg Interchange remains on schedule for pre June 2010 completion.
 
Things are progressing fast in CT, they're working around the clock to sort it out. I can't wait until it's over!

capetownguy: Would you know when Eastern Boulevard's outgoing nighttime backups, caused by all the lanes feeding into one, are going to end?
 
Cape Town opens first 2010 road infrastructure
Chantall Presence | 30 Minutes Ago

The City of Cape Town will be opening one of its first 2010 legacy roads on Thursday.

Granger Bay Boulevard runs from the V & A Waterfront precinct to the newly-raised Green Point circle, opposite the Cape Town Stadium.

The city’s Eddie Chinnappen said it was all systems go, contrary to reports that this and other world cup infrastructure initiatives were behind schedule.

“Granger Bay Boulevard at the moment is opened to traffic. The circle, which is a raised circle across the Western Boulevard, that’s also opened to traffic. So if you look at the percentage completion on both these projects, we’re fast approaching 90 percent, and we’re very close to completion,” said Chinnappen.
 