Call me selfish, but why t f should I suffer with other countries when the electricity resources are generated here in South Africa? !
Contractual obligations & severe penalties.
South Africa’s biggest forum. Discuss, discover, and connect with thousands of members.
Call me selfish, but why t f should I suffer with other countries when the electricity resources are generated here in South Africa? !
Contractual obligations & severe penalties.
Hehe.
You know, the achievements then are all the more amazing when you remember that it happened in Africa. With all our problems and issues and
deficits and "Spoories mentalities", the old ESCOM/EVKOM was an astonishing achievement.
We've been coasting on the momentum built up by that generation.![]()
Medupi, in Limpopo, was expected to be online by December 24.
“We may not meet the target, and could see Medupi coming online in early January
Yes, indeed - done with the spare capacity built up in the 80s. We actually had a serious over-capacity problem then. Which is why some stations were mothballed.By the end of the '80s, after nearly 100 years of power reticulation in South Africa, Eskom had only managed to connect 1/3 of its citizens.
A decade later, another 1/3 was connected (ie doubling the numbers in 10 years).
If there was ever an astonishing achievement for Eskom, it was in the '90s
By the end of the '80s, after nearly 100 years of power reticulation in South Africa, Eskom had only managed to connect 1/3 of its citizens.
A decade later, another 1/3 was connected (ie doubling the numbers in 10 years).
If there was ever an astonishing achievement for Eskom, it was in the '90s
When did they start with Medupi and Kusile?
When my ol'man was building powerstations in the 80s, they used to get 6 sets up and running within 8 years of sod turning.
I guess project management and engineering is in a severe decline.
2015 will be the year that our economy takes a huge nose dive and people get fired left, right and centre.
So much to look forward to!! Yay!![]()
I have to take exception to this comment. I am personally quite tired of all the assertions that the contractors are largely to blame for the delays at Kusile and Medupi.
First of all Kusile and Medupi are the largest coal fired power stations ever built in South Africa. Kusile will be 1.6 times larger than Duvha power station. It will also have a far more complex and modern Boiler than any power station in South Africa. So comparing the duration taken at Duvha, to Kusile is somewhat disingenuous. The closest power station we have in terms of capacity to that of Kusile is Kendal. Kendal is about 85% of the size of Kusile. It took 11 years to get Kendal online (1982 to 1993).
Kusile started in 2009. I expect it to be completed around 2020-2021, which will be 11-12 years, which is roughly the same time taken to build Kendal. So not that far off.
The same contractors that delivered the impressive World Cup Stadia (and related infrastructure) on time are the same ones building the power stations.
Something that should also be noted is that all the previous power stations (barring the latter half of Majuba) were built during Apartheid, when there were no restrictive labour laws in place. If you wanted to fire someone, you could. Someone was misbehaving? They would take them to a corner and slap them silly and you could all get along. The workplace was ruled with fear and subsequently you had a very dedicated work force, who feared that they may loose their job anytime.
Fast forward to now, where at Kusile it was practically impossible to fire someone. I had a labourer climb into a crane and operate it. We had a photograph of him doing so. At the hearing, the external guy threw the case out as he claimed, how does he know we did not photoshop the picture to implicate the guy. I mean really?
In 2011 and 2013 we had a series of strikes. The result was no labourer lost their job. They were given across the board increases and other incentives. No marked improvement in productivity was realised. In fact in terms of average civil construction productivity rates, at Kusile we are experiencing a productivity rate of 20% of what we get on our other projects outside of Kusile. Eksom has created a climate within Kusile where one can expect significant compensation, without giving anything in return.
We went through hell. I have on four occasions, literally dropped everything and run for my life from 5000+ angry striking workers. They have thrown stones at us. They have burnt down our offices, they have looted our offices, they have burnt out vehicles and other plant and simply just vandalised other infrastructure to blackmail Eskom into giving them more money.
Eskom implemented some of the strangest policies I have ever seen in the industry. Each and every step in the construction process had to have its usual quality inspection at the requisite hold point. However, Eskom required us to stop and then wait 4 hours before they would come and inspect the item. Never in the civil construction industry has this been a factor. It was not allowed for in the schedule or costing forecasts.
To give you an idea of the impact that this had, is that from 2010 to Feb 2014 for the Boiler Civil works (i.e. all the concrete works that support the main boiler steel and piping structures), we completed THREE of the 6 Units . In Feb 2014, we successfully argued with Eskom to remove this time restriction. From Feb 2014 to today, we completed the last THREE. Yes, it took us 3 years to do the first three units. It took us a year to do the last three. Substantial impact, that the four hour rule had on time!
So I take extreme exception to your assertions. The contractors at Kusile (and Medupi) have been thrown into a pit of fire and brimstone, forced to face a client who too often wants to please the country with unreal expectations, than to sit down and face the realities of what they want and how it will be achieved. In so doing they created the most apathetic labour force the construction industry has ever seen.
I get your point, but I was talking holistically (industry wide, end to end). Not about isolated pockets of excellence in the sea of mediocrity that is the SA labour force.
The contractors at Kusile (and Medupi) have been thrown into a pit of fire and brimstone, forced to face a client who too often wants to please the country with unreal expectations, than to sit down and face the realities of what they want and how it will be achieved. In so doing they created the most apathetic labour force the construction industry has ever seen.
Thanks for that insight, buka001.Eskom have lost a massive amount of capacity in terms of engineering and project management skills. Some of the field engineering guys (especially the Geotechnical Department) were appalling. Had absolutely no clue about the field in which they purportedly practice.
Nope, it's not an astonishing achievement at all, considering only a half-job was done.
The politically expedient, visible portion (delivery to end user) was done, with zero attention to the actual important stuff - the underlying infrastructure.
Not sure if the cANCer thought that electricity just appeared out of thin air (maybe that's why they want an investigation into lightning?)
Eskom have lost a massive amount of capacity in terms of engineering and project management skills. Some of the field engineering guys (especially the Geotechnical Department) were appalling. Had absolutely no clue about the field in which they purportedly practice.