Late at night has a 20GW load. We have about 18GW of coal, plus koeberg (1.8) and imports (1.3) minus pumped storage pumping back (2.5) - so we are always on the edge.
I'm talking about 23:00 to 3:00 or 4:00. Not sure we can trust the figures much anyway, the source can't be trusted.
 
They never promised that
View attachment 1402955

Ah, I misread the News24 post:

Eskom has announced that load shedding escalated to Stage 4 in the early hours of Tuesday morning.

"Stage 4 load shedding was implemented at 05:30 due to breakdowns of five generators at five power stations overnight. The load shedding will be implemented until further notice," spokesperson Sikonathi Mantshantsha said.

More information is expected to be provided later.

 
Kindly define "breakdown of five generators"... what got broken, and why, and how will it be fixed so as not to happen again in future?

Otherwise it's just pissing into the wind.
It's not just pissing in the wind anymore. At this point is shitting your mother-in-law's curry from last night into a tornado
 
They've not had a press conference for ages.
I saw him on one of the news channels about 2 days ago but I just caught the end.

I must say, the complex recipe for the next few days does suggest management are trying to make this less extreme.
 
Evening Peak Feedback 18/10/2022 18:38
Total demand: 30 532MW
Loadshedding: 4 147MW
Virtual Power Station: 250MW
Eskom OCGT's Utilised: 5
Renewable Gen: 1 146MW (Wind 873MW, CSP 273MW)
@Eskom_SA Available Generation Capacity: 27 664MW
@EskomSpokesper1

Come one guys who is running those aircons? :P
 
  • Like
Reactions: Yuu
Evening Peak Feedback 18/10/2022 18:38
Total demand: 30 532MW
Loadshedding: 4 147MW
Virtual Power Station: 250MW
Eskom OCGT's Utilised: 5
Renewable Gen: 1 146MW (Wind 873MW, CSP 273MW)
@Eskom_SA Available Generation Capacity: 27 664MW
@EskomSpokesper1

Come one guys who is running those aircons? :p

All those solar panels not working with the cloud cover today.
 
i dont understand how we can go from 5 units tripping and needing stage 4 to nothing during the day? surely those 5 units will take time to get back online?
 