Vumatel told MyBroadband that the issues suffered by several ISPs, which affected clients, over the weekend were mainly due to maintenance performed by a large third-party data centre.
Dear client
We would like to remind you that Teraco has scheduled planned major electrical maintenance at the JB1 Isando East Data Centre, the details are as follows:
Description
A-Feed Electrical Infrastructure Maintenance

  • Data Centre 2 (including Carrier Hotel 2)
  • Data Centre 3
  • Data Centre 4 (including Carrier Hotel 3)
  • Data Centre 5
Date
Saturday 17 November 2018
Time
08:00 22:00 SAST

Service Impact:
  • All single corded devices on this feed will be affected, please inquire with Teraco Support regarding an Automatic Transfer Switch for increased resilience.
  • No client installations to be undertaken during this period.
 