Let's be very clear about this. The city hired the experts of BRT.

What they did NOT do was effectively price the system.

When the tenders started coming in the prices were well above what was expected.

I think Eddie might take all the blame.

It remains my opinion that while the costs have changed, the problem is NOT the cost but trying to blame somebody and the city's "prudent" reaction to the costs. Under the new prudent approach they only make a "cost saving" of R40.2m which basically just for PR.

I think we have an incomplete flyover on our hands. What a let down after the all the other great work by the DA.
 
Another one? Ag no man, Cape Town really does not need another one :p

Child to parent: why does this red lane end here?
Parent to child: cape town actually once considered having a decent public transport system but instead of making the investment, got scared and abandoned the project like many city governments before it.
 
Transport Projects Update: 9 October 2009

PTIS 1: ITS


  • N1 CCTV: On schedule - February 2010
  • N2 Remote Monitoring: Complete
  • MTI Call Centre: Complete, in operation
PTIS 2: Project 2 - Airport to City road link

Hospital Bend

  • 75% complete
  • Funding: R13 million shortage (repairs to existing structure and resurfacing of existing roads to be omitted if funding not sourced)
N2 Outbound

  • 69% complete
  • Completion : End December 2009
N2 Bus Lane Inbound: Complete and in operation

PTIS 2: Project 3 - Klipfontein Corridor NMT Projects

Projects completed:

  • Bosduif/Petunia, Athlone Phase 1
  • Mowbray Liesbeek Parkway Phase 1
  • Spine Road Khayelitsha Phase 1
  • Hazel Road, Athlone
  • NY1 NMT Link Phase 2
  • Access to Red Cross Hospital
  • Spine Road Khayelitsha Phase 2
  • Bosduif/Petunia, Athlone Phase 2
Projects under construction:


  • Ingulube-Emms Drive: 40%
  • NY1 NMT Link Phase 2: 60%
  • Mowbray Liesbeek Parkway Phase 2: 55%
  • Big Lotus River: 50%
  • Nolungile Station: 15%
  • Nonqubela Station: 20%
PTIS 2 Granger Bay Boulevard


  • 70% complete
  • Opening, early December 2009
  • Funding: R18 million shortfall
  • Completion: February 2010
PTIS 2 CTIA IRT Project


  • Platform structure ahead of schedule, Target December 2009
  • Station structure: April 2010 Completion Target
PTIS 3 - Park and Ride (Rail based)


  • Kuils River Station: Ahead of schedule, February 2010
  • Monte Vista Station: Ahead of schedule, February 2010 (Work yet to start)
  • Brackenfell Station: On schedule, March 2010
  • Kraaifontein Station: On schedule, March 2010 (Work yet to start)
  • Ottery Station: April 2010 completion (Work yet to start)
  • Retreat Station: April 2010 completion (Work yet to start)
  • Landsdowne Station: Funding required
  • Fish Hoek Station: Funding required
  • Oosterzee Station: Funding required
  • Eerste Rivier Station: Funding required
PTIS 3 - Long Distance Bus Terminal


  • Work yet to start. Delays with PRASA
  • Tender evaluation in progress
  • May 2010 completion achievable
PTIS 3 - NMT Bridge Bhunga Avenue


  • All concrete works completed. Precast decks to be lifted end October
  • Cycle tracks: Ramps complete
  • Vygieskraal & Cornflower Culvert: Completion November 2009
  • Landscaping: 95% complete
  • Steel elements: November 2009
PTIS 3 - Road Signage Upgrade


  • M3, M5: Delays
  • M6, M7: Complete
  • M4: Behind schedule, November 2009 completion
  • R27, N1, N2: Underway
  • M62: Tender Awarded
  • CBD Signage: Tender closed
  • CBD and Stadium Event Signs: Tender to be awarded December 2009
PTIS 3 - Pedestrian Improvement: Stadium to CBD


  • Somerset Road to Ebenezer Road: End December 2009 completion
  • Ebenezer to Buitengracht: April 2010
  • Ebenezer realignment/works: Delayed
  • Somerset Pavement Widening: Heritage Complications
PTIS 3 - Pedestrian Improvement: Bridges


  • Buitengracht Bridge: 60% complete, February 2010 completion
  • Steel structure on site
  • Structure up by final draw but not operational
  • Waterkant Bridge: February 2010 completion
  • Waterkant Fan Walk NMT: Slightly behind schedule
PTIS 3 Koeberg Interchange


  • 50% complete
  • Ramp A completion date, April 2010
  • Roadworks: 65%
  • Ramp A: 51%
  • Ramp B: 41%
  • M5 viaduct: 34%
PTIS 3 Table Bay Boulevard


  • 56% complete
  • May 2010 completion
  • Lighting : January 2010
General IRT Works


  • Inner City Depot: Behind schedule
  • Negotiations with Transnet underway
  • Tenders Awarded for Inner City IRT Works from Hertzog Boulevard to Western Boulevard
  • Feeder stops have been verified
  • Hertzog Boulevard Station and Bus Way: May 2010
 
Some of the bicycle lanes around the stadium are already complete.

Here is the NMT(non motorized thread)

http://www.skyscrapercity.com/showthread.php?t=918996


The red lanes are special surfaces to cope with the heavier IRT buses.

There is an IRT thread open and one open at SSC too

http://www.skyscrapercity.com/showthread.php?t=768440

Thanks but what I want to know is if the NMT routes outside of the CBD are still going to get finished? A few routes around the stadium is pretty useless to someone who wants to come into town on a bicycle
 
Thanks but what I want to know is if the NMT routes outside of the CBD are still going to get finished? A few routes around the stadium is pretty useless to someone who wants to come into town on a bicycle

This is all the information I have. The IRT routes will have cycle lanes and pedestrian lanes

PTIS 2: Project 3 - Klipfontein Corridor NMT Projects

Projects completed:

* Bosduif/Petunia, Athlone Phase 1
* Mowbray Liesbeek Parkway Phase 1
* Spine Road Khayelitsha Phase 1
* Hazel Road, Athlone
* NY1 NMT Link Phase 2
* Access to Red Cross Hospital
* Spine Road Khayelitsha Phase 2
* Bosduif/Petunia, Athlone Phase 2

Projects under construction:

* Ingulube-Emms Drive: 40%
* NY1 NMT Link Phase 2: 60%
* Mowbray Liesbeek Parkway Phase 2: 55%
* Big Lotus River: 50%
* Nolungile Station: 15%
* Nonqubela Station: 20%
 
Basically, where there are IRT routes there are cycle routes. So when completed, you can cycle from Bayside to the CBD.
 