Eskom will implement load-shedding again on Tuesday evening

lol they don't even want to admit if it was tripped or taken offline for repairs:

Grootvlei and Matla power stations either tripped or were taken offline for repairs,” Eskom said in a statement.
Maybe they're unsure
 
lol they don't even want to admit if it was tripped or taken offline for repairs:

Grootvlei and Matla power stations either tripped or were taken offline for repairs,” Eskom said in a statement.
Grootvlei is like 200MW per unit and Matla would be up to 600MW a unit, so those are the ones we worry about. Camden, Grootvlei, Komati and Hendrina have smaller units, so a unit off there won't causing load shedding.
 
Evening Peak Feedback 10/05/2022, 17:59
Total Demand: 31 946MW
Loadshedding: 2 100MW
Virtual Power Station: 227MW
Eskom OCGT's Utilised: 13
IPP OCGT's Utilised: 6
Renewable Gen: 689MW (Wind 431MW, CSP 258MW)
@Eskom_SA Available Generation Capacity: 29 676MW

Not sure for how long they can burn diesel at this rate...
 
Evening Peak Feedback 10/05/2022, 17:59
Total Demand: 31 946MW
Loadshedding: 2 100MW
Virtual Power Station: 227MW
Eskom OCGT's Utilised: 13
IPP OCGT's Utilised: 6
Renewable Gen: 689MW (Wind 431MW, CSP 258MW)
@Eskom_SA Available Generation Capacity: 29 676MW

Not sure for how long they can burn diesel at this rate...
From the data sheet, for the week before they were only burning it during peaks, so not all day.
 