I have been waiting for 4 years to get fibre in my street and the trenching has just started outside since last week. I thought I should document the progress so others may benefit from the timelines from trenching in the street to actual fibre going live in a home. SADV is the installer of the backbone and they are trenching on the verges outside. They are not cutting across driveways but are horizontal directional drilling (boring) under the driveway which saves time and money in reinstating driveways.
We noticed the contractor's vans on the street on 11th of August. The next day they handed out flyers, marked and netted the verges and then the trenching started. I will document as much as possible.
Edit: please note that cm was changed to mm in the posts below in reference to trench depths.
We noticed the contractor's vans on the street on 11th of August. The next day they handed out flyers, marked and netted the verges and then the trenching started. I will document as much as possible.
Edit: please note that cm was changed to mm in the posts below in reference to trench depths.