Please do not touch Unit 2 before Unit 1 has been thoroughly tested! With all the "unplanned outages" you wouldn't want to be caught with your pants down and your mouth in the feeding trough!
 
Koeberg return delayed

Eskom is confident that Koeberg Power Station's two nuclear generators will be operational in time to renew the power station's operating licence.

However, the synchronisation of its Unit 1 generator has been delayed as it has yet to be fully synchronised to the grid.
Saw in some lecture, the last minute or so before the Chernobyl reactor literally ripped itself apart, it produced close to half a terrawatt of "electricity" (thermal power).

"the power jumped to about 100 times the rated power, in about 4 seconds"

These things are unbelievably powerful.

Without those control rods you have the opposite of loadshedding...

Found the lecture, it's from MIT open courseware

 
Last edited:
I hope they give an early warning to the general public when they actually do try to bring back online so people can evacuate.
 
However, the synchronisation of its Unit 1 generator has been delayed as it has yet to be fully synchronised to the grid.
uhh...that makes no sense. Either you're synchronized or you're not. There's no "slightly synchronized". So the synchronization has been delayed because it's not synchronized?
 