Due to delays in construction on two sections of Johannesburg's M1 highway‚ motorists can expect little relief in peak-hour traffic in coming months.
The Johannesburg Roads Agency (JRA) announced the progress it has made on the rehabilitation projects on Thursday.
JRA managing director Sean Phillips said the delays are the result of geotechnical complications on the Oxford and Federation road bridges project‚ near Killarney‚ and financial difficulty on the Double Decker bridge project‚ over the city centre.
The Oxford and Federation road bridge construction was expected to be completed by February next year. The deadline has now been extended to September 2017. Striking workers also delayed work here for six weeks between April and August.