It was this one but it looks like they are no more...pity as with a small gate motor battery its lasts the whole night...which is needed in a country where you darent open your windows at night... :ROFL:

 
Where can I find the number of hours of loadshedding from a specific date until today?

Work have an issue with the number of hours the generator have run, they cannot believe it have already done more than 250hrs.
Im also shocked... So little... :laugh:
 
Where can I find the number of hours of loadshedding from a specific date until today?

Work have an issue with the number of hours the generator have run, they cannot believe it have already done more than 250hrs.
Well there's been ovet 2400 hours of load shedding. If it's average stage 2, then it's an average of 1/8th of the time. So 2400/8 = 300
 
Where can I find the number of hours of loadshedding from a specific date until today?

Work have an issue with the number of hours the generator have run, they cannot believe it have already done more than 250hrs.

You could ask the Eskom Se Push people (for future reference).
 
EskomSePush has it in the app. 2458 hours so far this year.
Officially.
There's stolen cycle time (about 15 min. average for us), and an extra hour added about twice a month, and some shedding when there shouldn't be, and the very rare forgot to shed us.
:rolleyes:
 
FRI: Stage 1 until 4pm followed by stage 2 until midnight.
SAT&SUN: Stage 2 from midnight until 5am, then stage 1 until 4pm followed by stage 2 until midnight.
MON: Stage 2 until 5am with updates to follow.
 
Seems like demand has been dropping of late.
 