As I understand it, an entire cable is needed... Getting there I guess.Article said:Part of an underwater high-speed fibre-optic cable linking South Africa with the Americas and Europe will be completed by 2009
2009 is so damn far away... we need that thing completed ASAP!!!
The sooner it's completed, the sooner prices can drop more!
Then again one of the companies that lays the cables is owned by NeoTel's parent company VSNL so maybe they'll be more accommodating.As I understand it, there are only three companies that lay fiber undersea cables, and as it is there is a backlog. Secondly, it takes a few months to lay one cable, never mind 2. Also bear in that the landing stations also need to be built as well as all the infrastructure that needs to be put in the landing station itself. I think 2009 is actually a very ambitious target