[Update] More Stage 6 load-shedding this week

Bradley Prior

MyBroadband Journalist
Staff member
Super Moderator
Joined
Oct 16, 2018
Messages
5,033
Reaction score
1,585
Stage 6 load-shedding this week

Eskom has published a new load-shedding schedule that will be implemented immediately and will run until Thursday, 4 May 2023.

Update:

Eskom says stage 6 power cuts will continue — here is the new timetable

Eskom has announced that it will not decrease load-shedding on Thursday as planned and will instead maintain its alternating schedule of stage 4 and stage 6 power cuts.

The state-owned power utility said on Monday that it hoped to alternate between stage 3 and stage 5 on Thursday.
 
Last edited by a moderator:
fck. have bought fuel for genny. this is a real sh** show
 
The team is working around the clock to ensure that generating units are returned to service as soon as possible,” said Eskom.

Oh so that what is what they are doing. I thought they just pitch up for their monthly social grant.
 
The team is working around the clock to ensure that generating units are returned to service as soon as possible,” said Eskom.

Oh so that what is what they are doing. I thought they just pitch up for their monthly social grant.
They going to fix it nice
 
I can't quite place it, but I keep reading about stages 8, 9 and 11 somewhere. Some publication that keeps repeating it 500 times a day. :unsure:

It's odd though, because we only ever go to 6 :unsure:
 
I turned off my geyser

Switching mine on. And the kettle. Sorry.

I can't quite place it, but I keep reading about stages 8, 9 and 11 somewhere. Some publication that keeps repeating it 500 times a day. :unsure:

It's odd though, because we only ever go to 6 :unsure:

When we say have some Patience, we don't imply the local girl on the corner. Stay calm, watch some TV, winter is coming.
 
When we say have some Patience, we don't imply the local girl on the corner. Stay calm, watch some TV, winter is coming.
So it was more just a joke around MyBB's constant fear mongering (a poor one, looking back now), but in all honesty, I'm pretty sure the government gave Eskom a mandate to not go higher than stage 6.

They will rather do load curtailment and load reduction than push up to higher stages, looking at the past.
 
So it was more just a joke around MyBB's constant fear mongering (a poor one, looking back now), but in all honesty, I'm pretty sure the government gave Eskom a mandate to not go higher than stage 6.

They will rather do load curtailment and load reduction than push up to higher stages, looking at the past.
In reality they would need to, residential only uses 20% of the total power, you only gain so much from shedding them, the higher stages have also shown them it's diminishing returns with things like batteries, geysers, fridges and whatnot kicking in around the peaks anyway.
 
In reality they would need to, residential only uses 20% of the total power, you only gain so much from shedding them, the higher stages have also shown them it's diminishing returns with things like batteries, geysers, fridges and whatnot kicking in around the peaks anyway.
I'm glad I'm not the person in charge that has to determine what stage, load curtailment, or load reduction level we're on and who to cut. It must be a stressful job to try and keep everyone from residential to industry 'happy'.
 
In reality they would need to, residential only uses 20% of the total power, you only gain so much from shedding them, the higher stages have also shown them it's diminishing returns with things like batteries, geysers, fridges and whatnot kicking in around the peaks anyway.

I'm glad I'm not the person in charge that has to determine what stage, load curtailment, or load reduction level we're on and who to cut. It must be a stressful job to try and keep everyone from residential to industry 'happy'.

There is quite a large category of retail and light industrial, fed by the same zones and schedules as residential customers. Many of them have long since moved to generators to stay in business.

Some of the larger customers such as SAB Newlands moved to oil fired boilers which they use to generate stream. You can often see the initial black smoke as this starts up during load shedding.
 