Does anyone know when a rollout schedule will be released?
I think they're still awaiting some wayleaves from JRA :/
They are starting with the portion west of Delta Park though, already some digging happening.
Roll out has started.
Below is a link the a map, but please note that dates can still change.
https://www.google.com/maps/d/viewer?mid=zJfDAlrWataA.kaE8S-xFrmKs
Lekker, thank you sir
On the other hand, only phase 8 /cries
nameBL AG8 - Phase 8
descriptionConstruction Starts: 16 November
Fibre Ready: 2 Decembe
But that's not too bad. When "fibre ready" can we be switched on?
That is when they can start installing the final line to your house. But as mentioned, those times are subject to change. As rain etc can impact on the delivery time. But I am looking forward to Fibre being available![]()
you and me both
My question is once that final CPE install is done, is that it? we're on? Or do we need to wait for completion before the fibre can be lit?
Once they have completed your area, and you have the final line into the house, you will be lit up.
So you don't have to wait till next year, the first houses are expected to be on in November already.
BTW, you saw it here first. Click below to order your Fibre:
http://vumatel.us11.list-manage.com...513853121dab8743e4&id=f7fef0ec68&e=8af0668a26
THANK YOU FOR YOUR APPLICATION!
Nice. Hard to believe that last year this time we were still having meetings, trying to see who we should go with, now a year later, and Fibre is becoming a reality. Was a lot of work, and a lot of reading, but at least it is done.
You should send a big thanks you to Jed and them for making the BCA, would not be here were it not for them.
Absolutely. Also you and your committee! Without you, I'd be facing a future of escalating Telkom calls forever...
Do you still have fibre committee meetings? Wanna come to one and buy you all a round....
.....VUMA has really taken charge, and have been amazing.
Roll out has started.
Below is a link the a map, but please note that dates can still change.
https://www.google.com/maps/d/viewer?mid=zJfDAlrWataA.kaE8S-xFrmKs
8 here but I suspect the date is wrongEW - Phase 14
Could not be worse
8 here but I suspect the date is wrong
Please post construction and progress photos if you have them![]()
Trenching seems to be going well. They started in Colinton road today. Pity there was also a burglary this morning. #progressnotprogress