Just 365 days to World Cup kick-off
June 11, 2009 Edition 1
ANÉL LEWIS
IN JUST 365 days the first whistle of South Africa's 2010 World Cup will be blown, and Cape Town is on track to host the event that is expected to attract more than 150 000 visitors to the city.
President Jacob Zuma, Fifa president Sepp Blatter, Premier Helen Zille, Mayor Dan Plato, and chief executive of the 2010 Fifa World Cup Organising Committee South Africa, Danny Jordaan, are expected to celebrate the one year to kickoff at the Green Point stadium today.
The stadium, estimated to cost R4.5 billion, will host eight games, including a semi-final. While the opening match will be at Soccer City in Johannesburg, Cape Town will host its first match that same evening.
City 2010 spokesman Pieter Cronjé said the new Green Point stadium would be ready for handover on December 14.
"The stadium is over 70% complete at this stage. Major concrete work has been completed and only the finishing touches still need to be done. This includes the seating, lighting, cabling, completion of the VIP suites, external cladding and other facilities."
Work on the state-of-the-art roof is also on track and Cronjé said it would be finished by September.
While the roof will cover the stands, the pitch will remain open.
Although there will be 68 000 seats in the stadium when the 2010 matches kick off next year, the number of seats will be reduced to 55 000 after the event.
The roof and the lights from the stadium will only be visible from high vantage points, such as mountain tops.
It has been designed to limit the noise and visual impact of the stadium on the surrounding areas.
Cronjé said only two hours of construction time have been lost because of load shedding since work started in March 2007. Work was delayed for almost seven days at the start of the construction because of strikes by workers.
There has been one fatality at the stadium, where more than 2 500 workers have been employed.
A construction worker was killed when he was knocked down by a construction vehicle.
The stadium will also be used to enhance its neighbouring environment.
Cronjé said water from the stadium roof would be used to fill ponds on the Green Point Common which is being upgraded for 2010 and work on that should be completed by March 2010 "at the latest", Cronjé said. Various sport codes will have fields and facilities on the upgraded common which will also include public recreational spaces.
A contract has yet to be signed between the City of Cape Town and a consortium of Stade de France and South African sports marketing company SAIL to operate the stadium after the World Cup.
But the lease will run for 10 to 30 years and the operators will pay the city a third of the earnings made during this time.
Cronjé said the two leases, for the operation of the stadium and the Urban Park, would be signed once the public comment period had closed and the contract had been referred to council for approval.
[email protected]