Mr Yelland, anything will push it over the edge... also note that this figure is a bit over-zealous, even as little as 1500MW is going to push us into Stage 2. So should, we say, have extreme heat in Gauteng and everyone fires up their aircons, that will do it...
We also know its coming, and some of us are more prepared than we were last year.
I don't think he's suggesting that it's going to take a further 3000MW to bring back load shedding. He's simply stating that an increase in demand of around 3000MW is inevitable in the next week and given the amount of capacity currently down has to result in load shedding.
 
So the conveyor belt that was blamed for the recent round of shedding first started giving problems in October and instead of addressing it we wait until it fails in January.

This is as South African as maintenance can get. Instead of preventative its reactive.
The new CEO has already addressed the conveyor belt issue apparently. It uses the same system at Kusile.

He has already demanded that they start the process of building a redundant system immediately.
 
The new CEO has already addressed the conveyor belt issue apparently. It uses the same system at Kusile.

He has already demanded that they start the process of building a redundant system immediately.
Got a source on this?
 
Seems to have been an industry term since at least 2008
 
And they never know the causes... Amazing.

Of course they don't, they need time to troubleshoot. Don't be like those people in WA groups that want to know why the power is off and when in will be fixed 5 minutes after it went off, the technicians haven't even gotten into their vehicles yet.

I repeat: Troubleshooting takes time.
 
  • Like
Reactions: Yuu
Got a source on this?

Conveyer belt is mentioned in this article:
Meanwhile, after another disastrous failure of the coal conveyor belt feeding the Medupi power station, Eskom COO Jan Oberholzer told Cape Talk on Monday that coal handling at the power station will be redesigned.

Oberholzer said that one of Medupi's units should have been out of commission from this week for more than two months to implement design changes, but plans were put on hold due to the shortage of electricity in the system.
 
The new CEO has already addressed the conveyor belt issue apparently. It uses the same system at Kusile.

He has already demanded that they start the process of building a redundant system immediately.

It amazes me that our entire country, 57mil people (plus the rest here)... depend on a conveyor belt... talk about standing on one leg...
 
It amazes me that our entire country, 57mil people (plus the rest here)... depend on a conveyor belt... talk about standing on one leg...

What is also amazing is that this is a "new" conveyor that keeps breaking.
 
What is also amazing is that this is a "new" conveyor that keeps breaking.
Not amazing when you realise its been designed by a tenderpreneur company that has no cooking clue what it is doing most probably (probably a Zuma family company too)
 
Various parts of eThekwini Metro without power, but there is "no load shedding" right now.
Something is not right here.
 