Koeberg Unit 1 return delayed to November
South Africa’s Eskom Holdings SOC Ltd. expects to finish maintenance on the first of two units at its 1,940-megawatt Koeberg nuclear plant in November after delays doubled the time it’s taking to complete the work.
The steam generator replacement on unit one was scheduled to be finished in early June, but unanticipated logistical obstacles along with issues integrating a local workforce slowed the timeline, Keith Featherstone, Eskom’s chief nuclear officer, said Thursday in an online briefing.
[Bloomberg]
South Africa’s Eskom Holdings SOC Ltd. expects to finish maintenance on the first of two units at its 1,940-megawatt Koeberg nuclear plant in November after delays doubled the time it’s taking to complete the work.
The steam generator replacement on unit one was scheduled to be finished in early June, but unanticipated logistical obstacles along with issues integrating a local workforce slowed the timeline, Keith Featherstone, Eskom’s chief nuclear officer, said Thursday in an online briefing.