Frogfoot Port Elizabeth

Pppoe disconnected in Westering.

Why can't we have nice things?
 
Has someone gone through the Consumer Protection Act to see if something can be done about these guys?
Don't think it would solve our issue since some don't have a fallback provider in their area but giving them a deserved scare might wake them up
 
Has someone gone through the Consumer Protection Act to see if something can be done about these guys?
Don't think it would solve our issue since some don't have a fallback provider in their area but giving them a deserved scare might wake them up
Papers?

Government is useless..
 
Summerstrand no power since Friday 1:30pm

Frogfoot lasted 7 hours which is quite good (They resolved/removed the Summerstrand outage last night on status page randomly)

Interesting that Openserve is still running, 46 hours later probably thanks to generators at the exchange

I in no way expect more than a few hours backup on a consumer product, just making an observation
 
Summerstrand no power since Friday 1:30pm

Frogfoot lasted 7 hours which is quite good (They resolved/removed the Summerstrand outage last night on status page randomly)

Interesting that Openserve is still running, 46 hours later probably thanks to generators at the exchange

I in no way expect more than a few hours backup on a consumer product, just making an observation

FF did actually deploy a generator but had to get approval first because of the node location.

Code:
Outage Resolved

Outage title: Outage | PLZ | SummerStrand | Down
Service Type: FTTH
Outage ref (solid): FRG1632819
Impact start time: 2021-11-05 20:55
Impact stop time: 2021-11-06 17:24
Impact: (Down)

Outage Update
-- Loadshedding
-- Logged to FFMNT
-- Team was delayed due loadshedding in area. Awaiting additional updates.
-- A substation in the area has failed.
-- Team is currently liaising with the caretaker to determine if a generator deployment is feasible.
-- Tech is en route to warehouse to pick up a generator to deploy at summerstrand. 
-- Node is on generator. Outage Resolved.
 
FF did actually deploy a generator but had to get approval first because of the node location.

Code:
Outage Resolved

Outage title: Outage | PLZ | SummerStrand | Down
Service Type: FTTH
Outage ref (solid): FRG1632819
Impact start time: 2021-11-05 20:55
Impact stop time: 2021-11-06 17:24
Impact: (Down)

Outage Update
-- Loadshedding
-- Logged to FFMNT
-- Team was delayed due loadshedding in area. Awaiting additional updates.
-- A substation in the area has failed.
-- Team is currently liaising with the caretaker to determine if a generator deployment is feasible.
-- Tech is en route to warehouse to pick up a generator to deploy at summerstrand.
-- Node is on generator. Outage Resolved.
Hmm I tried this morning and ONT got no signal, will try again (trying to make inverter last so have unplugged all unused equipment
 
FF did actually deploy a generator but had to get approval first because of the node location.

Code:
Outage Resolved

Outage title: Outage | PLZ | SummerStrand | Down
Service Type: FTTH
Outage ref (solid): FRG1632819
Impact start time: 2021-11-05 20:55
Impact stop time: 2021-11-06 17:24
Impact: (Down)

Outage Update
-- Loadshedding
-- Logged to FFMNT
-- Team was delayed due loadshedding in area. Awaiting additional updates.
-- A substation in the area has failed.
-- Team is currently liaising with the caretaker to determine if a generator deployment is feasible.
-- Tech is en route to warehouse to pick up a generator to deploy at summerstrand.
-- Node is on generator. Outage Resolved.
Impressed that they made the effort though, we had the cell companies liaising to bring in their generators, up 15 flights of stairs! ouch

I think the cell companies are only powering the basics due to the small size of generators, I think Voda uses their node here for their FTTH
 