Just wanted to share my PE Frogfoot install timeline:
2 October 2019 - Ordered from Afrihost
8 October 2019 - Received appointment confirmation from Frogfoot/Closed Circuit PE for 23 October
23 October 2019 - Closed Circuit PE arrive for installation on time, 20 or so minutes later they say they do not have enough cable and will need to order more and come back tomorrow, few more minutes pass and they say we will be contacted about the rescheduled appointment.
25 October 2019 - Frogfoot/Closed Circuit PE finally rescheduled for 31 October
31 October 2019 - Phoned at 1pm saying will be late for 2pm appointment by like an hour. At 6pm they arrive and apologise and reschedule for next morning.
1 November 2019 - They arrived at appointment time (9am) and finished installing the line after 5pm.
2 October 2019 - Ordered from Afrihost
8 October 2019 - Received appointment confirmation from Frogfoot/Closed Circuit PE for 23 October
23 October 2019 - Closed Circuit PE arrive for installation on time, 20 or so minutes later they say they do not have enough cable and will need to order more and come back tomorrow, few more minutes pass and they say we will be contacted about the rescheduled appointment.
25 October 2019 - Frogfoot/Closed Circuit PE finally rescheduled for 31 October
31 October 2019 - Phoned at 1pm saying will be late for 2pm appointment by like an hour. At 6pm they arrive and apologise and reschedule for next morning.
1 November 2019 - They arrived at appointment time (9am) and finished installing the line after 5pm.